| 2019-10-08 16:38:24 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR |
| | MS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. WHERE DOES THE 15" RCP LEAVING THE SITE CONNECT TO? |
| | IS THERE A DRAINAGE EASEMENT FOR THIS PIPE AND/OR THE |
| | REST OF THE DRAINAGE SYSTEM? |
| | |
| | 2. EXFILTRATION TRENCH MAY NEED TO BE REPLACED OR |
| | CERTIFIED BY A PROFESSIONAL ENGINEER THAT IT IS |
| | FUNCTIONING PROPERLY. |
| | |
| | 3. INDICATE THE LOCATION OF THE DRAINAGE CONTROL |
| | STRUCTURE AND PROVIDE INFORMATION ON THE WEIR |
| | ELEVATION, RIM ELEVATION, ETC. |
| | |
| | 4. CONVERSION EQUATION BETWEEN NAVD1988 AND NGVD1929 |
| | SHOULD MATCH ON THE SURVEY AND ENGINEERING PLANS. |
| | |
| | 5. BELVEDERE ROAD IS MAINTAINED BY PALM BEACH COUNTY. |
| | ANY WORK WITHIN THE RIGHT OF WAY WILL REQUIRE A PERMIT |
| | FROM THE COUNTY. |
| | |
| | 6. SOUTH DIXIE HIGHWAY IS MAINTAINED BY FDOT. ANY WORK |
| | WITHIN THE RIGHT-OF-WAY WILL REQUIRE A PERMIT FROM |
| | FDOT. |
| | |
| | 7. EXPLAIN WHAT ARE THE MARKINGS THAT APPEAR TO BE |
| | CROSS WALK STRIPING. |
| | |
| | 8. EXPLAIN/LABEL THE ASPHALT CONNECTIONS TO BELVEDERE |
| | ROAD. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PERMIT MODIFICATION |
| | PRIOR TO STARTING CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |