| 2019-08-13 23:23:58 | THIS IS A CONCEPTUAL LEVEL REVIEW. |
| | CONSTRUCTION LEVEL DETAILS, DESIGN CALCULATIONS AND THE |
| | POLLUTION PREVENTION PLAN WILL BE REVIEWED AS PART OF |
| | THE ENGINEERING DEVELOPMENT APPROVAL AND BUILDING |
| | PERMIT APPLICATION PROCESSES. |
| | |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT HTTP://WPB.ORG/DEPARTMENTS/ENGINEE |
| | RING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. MISSING 1? 8? DIMENSION CALLOUT ON CWPB TYPICAL |
| | PARKING STALL DETAIL ON SHEET SP-1. |
| | |
| | 2. WEIR ELEVATIONS ARE HIGHER THATN PAVEMENT GRADE |
| | ELEVATIONS |
| | |
| | 3. IDENTIFY ON SHEETS P-3 AND P-4 WHICH EXFILTRATION |
| | TRENCH DETAIL (2A, 2B, 2C) PERTAINS TO EACH OF THE |
| | EXFILTRATION TRENCH SEGMENTS. |
| | |
| | 4. AT STRUCTURE D-205, PLACE WEIR ON THE WEST WALL AND |
| | A PRB ON THE SOUTH WALL. |
| | |
| | 5. INDICATE IF THERE IS AN OUTFALL FOR BASIN 2C |
| | EXFILTRATION TRENCH. |
| | |
| | 6. THERE IS A MODIFIED EXFILTRATION TRENCH EQUATION |
| | WHEN (DS > DU) OR (W > 2* [DU + DS]). |
| | |
| | 7. VERIFY DRAINAGE STRUCTURES ARE LARGE ENOUGH FOR THE |
| | INSTALLATION OF MORE THAN ONE PRB OR PRB AND WEIR IN |
| | THE STRUCTURES. |
| | |
| | 8. PROVIDE CCTV VIDEO OF EXISTING DRAINAGE PIPES FROM |
| | THE ALLEY TO THE CANAL. |
| | |
| | 9. DRAINAGE SYSTEMS TO BE DESIGNED TO MEET SFWMD |
| | CRITERIA FOR STORMWATER QUALITY AND PEAK DISCHARGE FOR |
| | PRE- VS POST-DEVELOPMENT CONDITIONS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING |
| | CONSTRUCTION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |