Date Text
2019-08-13 23:23:58THIS IS A CONCEPTUAL LEVEL REVIEW.
 CONSTRUCTION LEVEL DETAILS, DESIGN CALCULATIONS AND THE
 POLLUTION PREVENTION PLAN WILL BE REVIEWED AS PART OF
 THE ENGINEERING DEVELOPMENT APPROVAL AND BUILDING
 PERMIT APPLICATION PROCESSES.
  
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT HTTP://WPB.ORG/DEPARTMENTS/ENGINEE
 RING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. MISSING 1? 8? DIMENSION CALLOUT ON CWPB TYPICAL
 PARKING STALL DETAIL ON SHEET SP-1.
  
 2. WEIR ELEVATIONS ARE HIGHER THATN PAVEMENT GRADE
 ELEVATIONS
  
 3. IDENTIFY ON SHEETS P-3 AND P-4 WHICH EXFILTRATION
 TRENCH DETAIL (2A, 2B, 2C) PERTAINS TO EACH OF THE
 EXFILTRATION TRENCH SEGMENTS.
  
 4. AT STRUCTURE D-205, PLACE WEIR ON THE WEST WALL AND
 A PRB ON THE SOUTH WALL.
  
 5. INDICATE IF THERE IS AN OUTFALL FOR BASIN 2C
 EXFILTRATION TRENCH.
  
 6. THERE IS A MODIFIED EXFILTRATION TRENCH EQUATION
 WHEN (DS > DU) OR (W > 2* [DU + DS]).
  
 7. VERIFY DRAINAGE STRUCTURES ARE LARGE ENOUGH FOR THE
 INSTALLATION OF MORE THAN ONE PRB OR PRB AND WEIR IN
 THE STRUCTURES.
  
 8. PROVIDE CCTV VIDEO OF EXISTING DRAINAGE PIPES FROM
 THE ALLEY TO THE CANAL.
  
 9. DRAINAGE SYSTEMS TO BE DESIGNED TO MEET SFWMD
 CRITERIA FOR STORMWATER QUALITY AND PEAK DISCHARGE FOR
 PRE- VS POST-DEVELOPMENT CONDITIONS.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP PRIOR TO STARTING
 CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120