| 2020-03-02 15:57:57 | COMMENT RESULTS, NEW COMMENTS AND FURTHER CLARIFICATION |
| | IN BOLD. |
| | 1. SATSIFIED. |
| | 2. SATSIFIED. |
| | 3. SATSIFIED. EXISTING STREET LIGHT POLES SHALL BE |
| | REPLACED WITH THE CITY APPROVED LIGHT POLE, PER CITY |
| | ENGINEERING REQUIREMENTS. |
| | LIGHT POLES TO BE REVIEWED THROUGH PERMITTING. |
| | 4. ONGOING. PLEASE PROVIDE PHOTOMETRICS FOR THE SITE |
| | AND ROW MEETING REQUIREMENT OF SECTION 94-113(B). |
| | PLEASE INCLUDE LIGHT POLE DETAILS FOR BOTH INTERNAL AND |
| | ROW LIGHT POLES. |
| | SEE NEW COMMENT #101 |
| | 5. PARTIALLY SATSIFIED. SIDEWALK MUST BE AT GRADE |
| | INCLUDING ACROSS PARKING INGRESS/EGRESS AREAS. IT |
| | APPEARS THERE ARE ISSUES AT THE GARAGE ENTRANCES THAT |
| | REQUIRE CURBING AND STAIRS. THIS WILL NEED TO BE |
| | ADJUSTED TO KEEP THE GRADE LEVEL. |
| | REPEAT COMMENT: THE DESIGN OF THE CURB CUT OFF OF |
| | TRINITY PLACE INTO THE PARKING GARAGE DOES NOT ALLOW |
| | FOR CONTINUOUS PEDESTRIAN TRAVEL. PLEASE REMOVE CURBING |
| | AS NECESSARY TO PERMIT FOR CONTINUOUS PATH OF TRAVEL |
| | FROM THE WESTERN BOUNDARY ALONG TRINITY PLACE. PLEASE |
| | REFLECT DESIGN WITH THE LANDSCAPE PLAN |
| | 6. SATSIFIED. |
| | 7. SATSIFIED. |
| | 8. SATSIFIED. |
| | 9. SATSIFIED. |
| | 10. SATSIFIED. |
| | 11. SATSIFIED. |
| | 12. SATSIFIED. |
| | 13. SATSIFIED. |
| | 14. SATSIFIED. |
| | 15. ONGOING. PLEASE SHOW PROPOSED LOCATION OF BACKFLOW |
| | PREVENTER AND TRANSFORMER AND OTHER ABOVE GROUND |
| | UTILITIES. PLEASE NOTE, LOCATION OF THESE UTILITIES |
| | SHALL REQUIRE COORDINATION WITH ENGINEERING, PUBLIC |
| | UTILITIES, AND PLANNING AND ZONING TO ENSURE LOCATION |
| | THAT DOES NOT IMPEDE THE PUBLIC REALM AND THAT ALL |
| | UTILITIES ARE PROPERLY SCREENED. |
| | |
| | 3/2/20: COORDINATE WITH CITY ENGINEERING FOR PLACEMENT |
| | WITHIN INTERIOR OF PARKING GARAGE IF AT ALL POSSIBLE TO |
| | KEEP UTILITIES OFF OF PUBLIC ROW . SEE NEW COMMENT #94 |
| | 16. SATSIFIED. |
| | 17. SATSIFIED. |
| | 18. SATSIFIED. |
| | 19. SATSIFIED. |
| | 20. SATSIFIED. |
| | 21. SATSIFIED. |
| | |
| | 22. SATSIFIED. |
| | 23. SATSIFIED. |
| | 24. SATSIFIED. |
| | 25. PARTIALLY SATSIFIED. THE CALCULATION FOR REQUIRED |
| | PARKING FOR MICRO-UNITS, STANDARD UNITS, AND |
| | RETAIL/COMMERCIAL ARE INCORRECT. THE PERMITTED PARKING |
| | FOR MICROUNITS IS 102 SPACES FOR UNITS AND 10 SPACES |
| | FOR GUESTS FOR A TOTAL OF 112 SPACES (ADJUST IN |
| | REQUIRED COLUMN). THE PERMITTED PARKING FOR STANDARD |
| | SPACES IS MIN. 14 AND MAX. 28 PLUS 1 SPACE FOR GUEST |
| | FOR A TOTAL OF 29 SPACES. THE PERMITTED PARKING FOR |
| | RETAIL IS MIN. 12 AND MAX. 24 (ROUNDED DOWN). PLEASE |
| | AMEND ACCORDINGLY AND NOTE THAT ANY PARKING SPACES |
| | ABOVE MAXIMUM PARKING SHALL COUNT TOWARDS FAR. THE |
| | NUMBER OF SPACES ARE ONLY ROUNDED UP IF DECIMAL POINT |
| | IS EQUAL TO OR ABOVE 0.5. |
| | |
| | 3/2/20: SEE NEW COMMENT # 87 |
| | 26. SATSIFIED. |
| | 27. SATSIFIED. |
| | 28. PARTIALLY SATSIFIED. PLEASE INDICATE THE LOCATION |
| | OF THE BIKE SHARE STATION ON THE SITE PLAN. EFFORTS CAN |
| | BE COORDINATED WITH THE CITY?S CURRENT BIKE SHARE |
| | PROGRAM. THE TOTAL NUMBER OF DOCKS REQUIRED WILL BE |
| | DETERMINED BY THE PROXIMITY OF OTHER BIKE SHARING |
| | STATIONS ALREADY INSTALLED WITHIN 500 FEET FROM THE |
| | SUBJECT PROJECT. |
| | |
| | 3/2/20: COORDINATE WITH KIMLEY-HORN ON LOCATION OF |
| | MICROMOBILITY STATION |
| | 29. SATSIFIED. |
| | 30. PARTIALLY SATSIFIED. PER SECTION 94-106(8A), THE |
| | REQUIRED BICYCLE PARKING FOR THE RESIDENTIAL |
| | MICRO-UNITS SHALL BE 0.5 BICYCLE PARKING SPACES PER |
| | MICRO-UNIT, WHICH WOULD BE 102 SPACES FOR THIS PROJECT. |
| | PLEASE REVISE ACCORDINGLY. THIS SHALL REQUIRE A COVERED |
| | AND ENCLOSED BICYCLE STORAGE AREA. |
| | |
| | 3/2/20: BICYCLE RACK POST SHALL BE MIN. 3 FEET AWAY |
| | FROM PERPENDICULAR WALL AND 2 FEET FROM PARALLEL WALL. |
| | 30? MINIMUM BETWEEN TWO RACK POSTS. PLEASE ADJUST AS |
| | NECESSARY ? THIS IS IMPORTANT FOR INSTALLATION |
| | |
| | 31. SATSIFIED. |
| | 32. SATSIFIED. |
| | 33. SATSIFIED. |
| | 34. SATSIFIED. |
| | 35. SATSIFIED. |
| | 36. SATSIFIED. |
| | 37. SATSIFIED. |
| | 38. SATSIFIED. |
| | 39. PARTIALLY SATSIFIED. PLEASE PROVIDE SPECIFIC |
| | ARCHITECTURAL DETAIL INCLUDING ALL MATERIALS AND |
| | INCLUDE REFERENCE IMAGES. STAFF HAS CONCERN OVER THE |
| | MATERIAL FOR THE GARAGE SCREENING AND NEEDS TO SEE MORE |
| | DETAIL OF THE SPACING OF THE FEATURES, PROPOSED |
| | MATERIAL, ETC. |
| | WAITING FOR UPDATED ARCHITECTURAL PLANS |
| | 40. PARTIALLY SATSIFIED. PLEASE CONSIDER ARCHITECTURAL |
| | FEATURES OTHER THAN GARAGE SCREENING ON THE PARKING |
| | GARAGE FA?ADE TO BETTER BLEND THE OBVIOUS FACADE OF |
| | PARKING GARAGE SCREENING AS SEEN FROM THE PUBLIC VIEW, |
| | ESPECIALLY FROM OLIVE AVENUE AND TRINITY PLACE, WHILE |
| | KEEPING THE MASSING DIFFERENT INTACT. |
| | WAITING FOR UPDATED ARCHITECTURAL PLANS |
| | 41. SATSIFIED. |
| | 42. PARTIALLY SATSIFIED. THE PARKING GARAGE RAMPS SHALL |
| | BE COVERED WITH ARCHITECTURAL TREATMENT. BLANK WALLS |
| | ARE NOT PERMITTED PER SECTION 94-109. NON-ACTIVE USES |
| | SHALL BE TREATED WITH ARCHITECTURAL TREATMENT PER TABLE |
| | IV-4. |
| | WAITING FOR UPDATED ARCHITECTURAL PLANS |
| | 43. SATSIFIED. |
| | 44. SATSIFIED. PLEASE EXTEND ARCHITECTURAL TREATMENT |
| | ALONG THE FA?ADE AREA ADJACENT TO THE PARKING GARAGE |
| | ALONG OLIVE STREET TO ALLEVIATE THE BLANK WALL. |
| | 45. ONGOING. PLEASE NOTE, PER RESOLUTION 211-17, |
| | PROJECTS WITH RESIDENTIAL MICRO-UNITS SHALL CONTRIBUTE |
| | A TROLLEY FEE AT $10 PER MICRO-UNIT PER MONTH. |
| | SHALL BE CONDITION OF APPROVAL |
| | 46. SATISFIED. |
| | 47. SATISFIED. |
| | 48. PARTIALLY SATISFIED. PLEASE SUBMIT STREET LEVEL |
| | RENDERINGS WITH RESUBMITTAL |
| | PLEASE INCLUDE THE CORRECT LIGHT POLE DESIGN, REMOVE |
| | THE LARGE TREE IF NOT BEING RELOCATED AND REPLACE WITH |
| | IMAGE OF PROPOSED TREE AT PLANTING HEIGHT. PLEASE |
| | ILLUSTRATE THE LANDSCAPE AT PLANTING HEIGHT. |
| | NEW COMMENTS DECEMBER 11, 2019: |
| | 49. ONGOING. PLEASE UPDATE THE RENDERING IF THE OAK |
| | TREE IS NOT BEING RELOCATED. |
| | 50. SATISFIED. |
| | 51. SATISFIED |
| | 52. ONGOING. PLEASE INDICATE WHAT MATERIAL WILL BE |
| | BEHIND THE BAMBOO SCREENING (IF ANY) |
| | WAITING FOR UPDATED ARCHITECTURAL ELEVATIONS SHOWING |
| | CMU WALL |
| | 53. SATISFIED. |
| | 54. ONGOING. PLEASE PROVIDE ADDITIONAL ARCHITECTURAL |
| | MATERIAL DETAIL |
| | WAITING FOR UPDATED ARCHITECTURAL ELEVATIONS |
| | 55. ONGOING. STAFF OVERALL FEELS THAT THERE IS A NEED |
| | FOR ADDITIONAL ARCHITECTURAL FENESTRATION AND TREATMENT |
| | ALONG THE NORTH, SOUTH AND WEST FA?ADE. ALTHOUGH SOME |
| | PORTIONS ARE INTERIOR LOT LINES, THE FACADES ARE BEHIND |
| | PARKING LOTS AND THE FA?ADE IS HIGHLY VISIBLE FROM THE |
| | STREET. LANDSCAPE MATERIAL AND PAINT CANNOT BE |
| | CONSIDERED AS TREATMENT FOR COVERING BLANK WALLS. THE |
| | TREATMENT ALONG THE NORTH PORTION OF THE EAST FA?ADE |
| | (THE PORTION WITH THE MESH GARAGE SCREENING) HAS |
| | ACCOMPLISHED THE CONTINUATION OF THE FEATURES |
| | THROUGHOUT THE ENTIRE FA?ADE, EFFICIENTLY BLENDING THE |
| | PORTION OF THE PARKING GARAGE INTO THE RESIDENTIAL |
| | UNITS IN THE UPPER FLOORS (GARAGE OPENINGS SAME SIZE AS |
| | WINDOWS ON UPPER FLOORS). THE PORTIONS OF PARKING |
| | GARAGE ALONG THE OTHER FACADES HAS DIFFERENT PATTERN |
| | THAN THE UPPER FLOORS, AND DOES NOT TREAT THE PARKING |
| | GARAGE PORTION AS EFFICIENTLY. PLEASE CONSIDER THE |
| | PATTERN OF PARKING GARAGE SCREENING OPENINGS AND |
| | CONSIDER INCLUSION OF ADDITIONAL ARCHITECTURAL |
| | TREATMENT ALONG NON-ACTIVE USES AND FENESTRATION ALONG |
| | ACTIVE USES (SEE TABLE IV-4). CAN OTHER MATERIAL |
| | BESIDES STUCCO BE USED ALONG FACADES? |
| | WAITING FOR UPDATED ARCHITECTURAL ELEVATIONS |
| | 56. ONGOING.PLEASE PROVIDE MORE INFORMATION ON THE |
| | PROPOSED PARKING GARAGE MESH SCREENING INCLUDING THE |
| | DISTANCE SEPARATION BETWEEN THE MESH FRAMES. IS THERE |
| | AN ALTERNATIVE SCREENING THAT CAN BE USED THAT BETTER |
| | SERVES AS FAUX WINDOWS OR CONTINUATION? |
| | WAITING FOR UPDATED ARCHITECTURAL ELEVATIONS |
| | 57. SATISFIED. |
| | 58. SATISFIED. |
| | 59. ONGOING.PLEASE PROVIDE SCREENING FOR THE ROOF |
| | MOUNTED MECHANICAL EQUIPMENT. PLEASE MAKE NOTE ON THE |
| | PLANS THAT THE ELEVATOR SHAFTS AND ALL PROJECTING |
| | OBJECTS ON THE ROOF WILL NEED TO BE PAINTED TO MATCH |
| | THE BUILDING FA?ADE COLORS OR OTHERWISE PROPERLY |
| | SCREENED. |
| | WAITING FOR UPDATED ARCHITECTURAL ELEVATIONS |
| | 60. SATISFIED. |
| | 61. NOT SATISFIED. THE PORTION OF THE GROUND FLOOR OPEN |
| | SPACE THAT IS BEING COUNTED TOWARDS THE REQUIRED |
| | PERCENTAGE OF PRIVATE OPEN SPACE MUST BE TREATED AS A |
| | SPECIFIC TYPE OF PUBLIC OPEN SPACE THAT IS PERMITTED IN |
| | THIS ZONING DISTRICT (SEE TABLE IV-6), NOT AS A |
| | SEMI-PUBLIC OPEN SPACE. SPECIFIC DETAILS ON THE PUBLIC |
| | OPEN SPACE TYPE MUST BE INCLUDED (SEE TABLE IV-7). |
| | MUST BE PUBLIC, NOT SEMI PUBLIC AND MEETING THE |
| | REQUIREMENTS FOR VEGETATION AND TREE CANOPY (MINIMUM |
| | SIZE DOES NOT HAVE TO BE MET) |
| | 62. SATISFIED. |
| | 63. SATISFIED. |
| | 64. NOT SATISFIED. PLEASE AMEND THE TRUNCATED DOME AND |
| | ADA RAMP AT THE PEDESTRIAN CROSSING SOUTH ACROSS |
| | TRINITY PLACE AND TANGLEWOOD COURT TO PROVIDE STRAIGHT |
| | ACCESS ACROSS TRINITY AND OLIVE STREET. |
| | PER MEETING WITH ENGINEERING DEPARTMENT, ADA CROSSING |
| | SHALL FACE DIRECTLY SOUTH. |
| | 65. SATISFIED. |
| | 66. ONGOING. PLEASE UPDATE THE ARCHITECTURAL SHEET |
| | A1-01 TO MATCH THE UPDATED SITE PLAN DATA |
| | SEE NEW COMMENTS REGARDING PARKING DATA |
| | 67. SATISFIED |
| | 68. SATISFIED |
| | 69. SATISFIED |
| | 70. SATISFIED |
| | 71. SATISFIED |
| | 72. SATISFIED |
| | 73. SATISFIED |
| | 74. NOT SATISFIED. STAFF RECOMMENDS INCORPORATING ANTI |
| | SKATEBOARD BARRIERS ON THE SEATS IN THE OPEN SPACE- |
| | MAKE NOTES ON THE PLANS IF ADDING |
| | COMMENT WAS NOT ACCURATELY RESPONDED TO IN COMMENT |
| | RESPONSE MEMO |
| | 75. NOT SATISFIED. PLEASE PROVIDE CONTEXTUAL ELEVATIONS |
| | NEED CONTEXTUAL ELEVATIONS NOT RENDERINGS |
| | 76. ONGOING. PLEASE EVALUATE THE OPPORTUNITY TO |
| | INCORPORATE THE BACKFLOW PREVENTER INTO FOUNDATION |
| | LANDSCAPE BED, CLOSER TO THE BUILDING. ALTERNATIVELY, |
| | ANY SOLUTION WHICH ALLOWS IT TO BE SCREENED ON AT LEAST |
| | THREE SIDES BY LANDSCAPE. PLEASE INDICATE PROPOSED |
| | SCREENING ON LANDSCAPE PLANS. |
| | CONVERSATION ONGOING WITH CITY ENGINEERING DEPARTMENT |
| | AND KIMLEY HORN TO LOCATE WITHIN PARKING GARAGE |
| | INTERIOR IF POSSIBLE |
| | 77. SATISFIED. |
| | 78. NOT SATISFIED. THE NUMBER OF MINIMUM AND MAXIMUM |
| | STANDARD PARKING SPACES FOR RETAIL, RESTAURANT OR |
| | COMMERCIAL SHOULD BE 17 AND 35 PLEASE AMEND |
| | PROVIDED COMMERCIAL PARKING SPACES EXCEED MAXIMUM |
| | REQUIRED. SEE NEW COMMENT #87 |
| | 79. SATISFIED |
| | 80. SATISFIED |
| | 81. SATISFIED |
| | 82. SATISFIED |
| | 83. SATISFIED |
| | 84. SATISFIED |
| | NEW COMMENTS MARCH 2, 2020: |
| | 85. RESTROOM AREAS ON LEVEL 4 ARE COUNTED TOWARDS FAR. |
| | PLEASE ADJUST FAR SHEET PZ-01 ? THIS WILL PUT THE |
| | PROJECT OVER THE PERMITTED FAR ? NEED TO ADJUST |
| | ELSEWHERE TO REMAIN UNDER MAXIMUM FAR |
| | 86. FOR THE MAINTENANCE OFFICE AND POOL EQUIPMENT ROOM, |
| | PLEASE ADD A NOTE THAT ?ROOM SHALL BE NOT UNDER AC? |
| | 87. THE PROVIDED COMMERCIAL SPACES EXCEED THE MAXIMUM |
| | SPACES REQUIRED. ANY PARKING SPACES ABOVE THE MAXIMUM |
| | SHALL BE COUNTED TOWARDS FAR. |
| | 88. ALL MECHANICAL EQUIPMENT MUST BE SCREENED ? PLEASE |
| | RAISE PARAPET TO COVER |
| | 89. COORDINATE ARCHITECTURAL PLANS WITH KIMLEY-HORN |
| | PLANS FOR MICRO MOBILITY SPACE |
| | 90. INCLUDE DOUBLE STRIPING WITHIN PARKING GARAGE |
| | MEETING STRIPING DETAIL REQUIREMENTS OF CITY OF WPB. |
| | 91. IN REGARD TO THE COMPACT PARKING SPACES THAT ARE |
| | AGAINST THE WEST WALL, SOUTH OF THE BICYCLE RACK ROOM: |
| | AS THIS IS A DEAD-END, ONE OF THE SPACES NEED TO BE A |
| | TURNAROUND SPACE (DIAGONALLY STRIPED) WITH A MINIMUM 3 |
| | FOOT BACKUP SPACE. |
| | 92. APPEARS TO BE BOLLARDS UP AGAINST THE TRASH ROOM |
| | AND DOOR TO THE BICYCLE RACK ROOM ON THE FIRST LEVEL OF |
| | PARKING GARAGE: THESE BLOCK ACCESS TO THE NORTHERN |
| | PARKING SPACE AND DON?T ALLOW FOR SUFFICIENT BACK UP |
| | SPACE. THE PARKING SPACES THAT ARE UP AGAINST THE |
| | SOUTHERN WALL ON THE BUILDING RAMPS ON THE OTHER FLOORS |
| | HAVE THE SAME ISSUE. THE VEHICLES PULLING OUT OF THIS |
| | SPACE WOULD HAVE TO PACK UP STRAIGHT INTO THE OPPOSITE |
| | TURN LANE, UP THE RAMP IN ORDER TO GET OUT OF THE |
| | SPACE. THESE WILL NEED TO BE REMOVED OR RELOCATED |
| | APPROPRIATELY |
| | 93. COORDINATION FOR SIDEWALK ALONG TRINITY PLACE |
| | ONGOING WITH CITY ENGINEERING AND KIMLEY HORN TO ALLOW |
| | FOR CONTINUOUS PEDESTRIAN PATHWAY ALONG SIDEWALK. |
| | 94. LOCATE WATER METER AND BACKFLOW PREVENTER WITHIN |
| | PARKING GARAGE IF POSSIBLE ? COORDINATE WITH CITY |
| | ENGINEERING |
| | 95. THE PARKING SPACES THAT ARE UP AGAINST THE SOUTHERN |
| | WALL ON THE BUILDING RAMPS DO NOT WORK. THE VEHICLES |
| | PULLING OUT OF THIS SPACE WOULD HAVE TO PACK UP |
| | STRAIGHT INTO THE OPPOSITE TURN LANE, UP THE RAMP IN |
| | ORDER TO GET OUT OF THE SPACE. PLEASE ADJUST AS |
| | NECESSARY |
| | 96. PLEASE LOCATE EXHAUST FAN TO FACE WEST IF POSSIBLE |
| | RATHER THAN SOUTH TO TRINITY PLACE. PLEASE SHOW ON |
| | ARCHITECTURAL ELEVATIONS |
| | 97. PLEASE CLARIFY USE OF STORAGE CASES WITHIN PARKING |
| | GARAGE THAT STILL HAVE COMPACT PARKING SPACES WITHIN? |
| | 98. PLEASE NOTE, STAFF WILL REQUEST AN UPDATED |
| | RENDERING WITH THE PROPOSED PARKING GARAGE SCREENING |
| | DURING THE PERMITTING PROCESS, OR IF ARTIST AND DESIGN |
| | IS PICKED AFTER THE PERMIT PROCESS, THIS SHALL BE |
| | SUBMITTED PRIOR TO CO AS A PERMIT REVISION. |
| | 99. THE NUMBER OF REQUIRED CAR SHARING IS BASED ON |
| | MICRO-UNITS NOT STANDARD UNITS, SO 15 CAR SHARING |
| | SPACES ARE REQUIRED. THE CAR SHARING REDUCTION IS 7 NOT |
| | 8. THIS RESULTS IN A MAXIMUM OF 184 PARKING SPACES. |
| | PLEASE ADJUST NUMBERS ACCORDINGLY IN PARKING TABLE. |
| | 100. PLEASE MATCH KIMLEY-HORN PLANS TO ARCHITECTURAL |
| | PLANS IN REGARD TO BICYCLE RACK ALONG THE ROWS. |
| | 101. STREET LIGHTING TO BE REVIEWED AT TIME OF |
| | PERMITTING. PHOTOMETRICS NEED TO INCLUDE PUBLIC OPEN |
| | SPACE AREA ALONG OLIVE AVENUE. LIGHT POLES ARE MISSING |
| | FROM TRINITY PLACE. |
| | 102. A FEE OF $300 IS REQUIRED FOR ANY RESUBMITTAL |
| | BEYOND THE SECOND SUBMITTAL. PLEASE SUBMIT A CHECK FOR |
| | $300 WITH RESUBMITTAL. |
| | |
| | STAFF RESERVES THE RIGHT FOR FURTHER COMMENT AS THE |
| | REVIEW PROGRESSES. |
| | |
| |