| Plan Review Notes For Project Z19050026 |
| Project Number |
Z19050026 |
|
| Review Stop |
STORM |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2019-10-09 09:05:57 | THE FOLLOWING COMMENT IS FROM THE REVIEW OF THE | | | 10/4/2019 REVIEW SET OF PLANS: | | | | | | 1. INDICATE HOW STORM WATER QUALITY TREATMENT IS BEING | | | PROVIDED FOR THE AREA OF NEW CONSTRUCTION. IF EXISTING | | | EXFILTRATION TRENCH IS BEING USED THEN A PROFESSIONAL | | | ENGINEER WILL NEED TO CERTIFY THE SYSTEM IS FUNCTIONING | | | PROPERLY. | | | | | | 2. SPECIAL PURPOSE SURVEY NOT INCLUDED IN THE SUBMITTAL | | | SO STAFF CANNOT DETERMINE IF PREVIOUS COMMENTS HAVE | | | BEEN ADDRESSED. | | | | | | TRACY WARD, PE | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 | | | [email protected] | | | |
| |
Print |
|