| Plan Review Notes For Project Z19050020 |
| Project Number |
Z19050020 |
|
| Review Stop |
SURVEY |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2019-09-11 07:41:44 | 1. REMOVE VAULT FROM SIDEWALK AREA. APPROVAL FROM MARK | | | HURLEY, CUSTOMER SERVICE, WILL BE REQUIRED FOR | | | METER/BACKFLOW ASSEMBLY. | | | 2. CANOPY MAY REQUIRE AN AERIAL ENCROACHMENT EASEMENT. | | | 3. A LANDSCAPE/HARDSCAPE MAINTENANCE AGREEMENT WITH | | | FDOT WILL BE REQUIRED. THE APPLICANT NEEDS TO PROCESS | | | APPLICATION WITH FDOT FOR THE CITY TO APPROVE. THE | | | OWNER WITH THEN ASSUME OBLIGATIONS OF THAT AGREEMENT | | | AND ANY OTHER RIGHT-OF-WAY MAINTENANCE OBLIGATIONS | | | THROUGH A SEPARATE AGREEMENT WITH THE CITY. |
| |
Print |
|