2019-08-14 15:19:01TRAFFIC STUDY COMMENTS:
 1. THE TRAFFIC STUDY SHOULD BE THOROUGHLY CHECKED BY
 THE PE TO MAKE SURE THE TRAFFIC ANALYSIS IS COMPLETED
 CORRECTLY AND PROPERLY REFLECTS THE EXPECTED TRAFFIC
 CONDITIONS.
 2. CLARIFY IF THE PROJECT TRIPS INCLUDE CIRCULATION DUE
 TO VALET VEHICLES, AND HOW MANY (OR PERCENTAGE OF)
 VALET VEHICLES ARE EXPECTED. IF NOT, PLEASE INCLUDE
 VALET VEHICLES IN PROJECT TRIP CALCULATIONS. ALL VALET
 VEHICLES BOUND FOR PICK-UP WOULD NEED TO CIRCULATE
 AROUND THE BLOCK USING FERN STREET, ROSEMARY AVENUE AND
 HIBISCUS STREET AND DEPART FROM SAPODILLA
 AVENUE/HIBISCUS STREET. ALL VALET VEHICLES BOUND FOR
 DROP-OFF WOULD NEED TO ACCESS THE VALET AREA FROM
 ROSEMARY AVENUE/HIBISCUS STREET.
 3. THE TRIP GENERATION RATE FOR LAND USE CODE 710
 OFFICE SHOULD BE BASED ON GROSS FLOOR AREA. THE SITE
 PLAN SHOWS A GFA OF 56,928 SF BUT 51,250 SF IS USED IN
 THE TRIP GENERATION ANALYSIS. PLEASE REVISE.
 4. THE TRIP GENERATION RATE FOR LAND USE CODE 820
 SHOPPING CENTER SHOULD BE BASED ON GROSS LEASABLE AREA.
 PLEASE VERIFY AND REVISE.
 5. TRIP GENERATION CALCULATIONS FOR SOME OF THE LAND
 USES DO NOT APPEAR TO BE CONSISTENT, E.G. THE APARTMENT
 LAND USE DURING PM PEAK HOUR. ALSO, THE PASS-BY
 PERCENTAGE FOR SHOPPING CENTER DEPENDS ON THE INTENSITY
 AND SHOULD BE VERIFIED IF THE INTENSITY IS CHANGED.
 6. IN THE INTERNAL TRIP CALCULATION, PLEASE CLARIFY THE
 SOURCE OF THE 12% UNCONSTRAINED INTERNAL TRIP CAPTURE
 RATE BETWEEN EACH INDIVIDUAL USE. ITE TRIP GENERATION
 HANDBACK 3RD EDITION SUGGESTS DIFFERENT PERCENTAGES.
 7. IN THE SYNCHRO ANALYSIS AT OKEECHOBEE
 BOULEVARD/TAMARIND AVENUE, ADD WBU VOLUMES ONTO WBL
 VOLUMES AND REMOVE WBU SINCE U-TURN CAUSES ISSUES WITH
 HCM 2000 ANALYSIS IN SYNCHRO, WHICH RESULT IN
 UNREALISTIC DELAYS. APPROPRIATE SIGNAL TIMING SHOULD BE
 USED. ALSO, PLEASE ASSUME 2 NORTHBOUND LANES WHICH IS A
 COMMITTED OFF-SITE IMPROVEMENT FROM THE KRAVIS CENTER
 DEVELOPMENT IN THE FUTURE YEAR ANALYSIS.
  
 CONDITIONS:
 1. PRIOR TO ISSUANCE OF THE FIRST CERTIFICATE OF
 OCCUPANCY, EVALUATE AND REMOVE ALL-WAY STOP AND CONVERT
 TO TWO-WAY STOP AT THE SOUTHWEST CORNER OF THE SITE IF
 ALL-WAY STOP IS NOT WARRANTED.
  
  
 SHING TSOI
 CITY IN-HOUSE TRAFFIC CONSULTANT
 561-494-1141
 [email protected]
 (IN-HOUSE ON TUESDAYS AND WEDNESDAYS)
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved