| 2019-08-16 07:13:16 | 1. PLEASE RESPOND TO ALL COMMENTS IN WRITING, AND |
| | INCLUDE PROJECT NAME, ADDRESS AND PERMIT NUMBER |
| | (Z-XXXXXXXX). |
| | |
| | 2. PLANS SHALL SHOW PROPOSED LOCATIONS AND DIMENSIONS |
| | OF ALL WATER, STORM WATER, AND SANITARY AND SEWER |
| | LINES, INCLUDING STUBS TO EACH PROPERTY LINE FOR WATER |
| | AND SANITARY SEWERS, THE MAKE AND MODEL OF ALL VALVES, |
| | METERS, AND OTHERS DEVICES TO BE INSTALLED ON THE |
| | SYSTEM, CATCH BASINS, CULVERTS, DITCHES INCLUDING |
| | GRADES, PIPES SIZES, MATERIALS, ELEVATIONS, |
| | ASSUMPTIONS, CALCULATIONS, INVERT ELEVATIONS FOR ALL |
| | INLETS AND MANHOLES AND PROFILES OF SANITARY SEWER |
| | LINES. ALL AVAILABLE ELEVATION SHALL BE SHOWN ON THE |
| | PROFILE VIEW. DIRECTION OF FLOW SHALL BE SHOWN ON PLAN |
| | VIEW ON PLAN VIEW FOR ALL SANITARY AND STORM SEWERS. |
| | ADDITIONALLY, PLAN VIEW SHALL SHOW ALL EXISTING AND |
| | PROPOSED UNDERGROUND UTILITY LAYOUT, INCLUDING FIBER |
| | OPTIC, ELECTRIC, GAS, AND CABLEVISION & |
| | TELECOMMUNICATION FACILITIES LOCATED ON THE |
| | RIGHT-OF-WAY (NOTE: SURVEY SHOWS TWO AT&T VAULTS IN |
| | GARDENIA ST. RIGHT OF WAY NEAR PROPOSED WATER AND |
| | SANITARY SEWER WORK, THAT ARE NOT REFLECTED ON |
| | PRELIMINARY UTILITY PLANS). PROVIDE PROFILE AND |
| | CLEARANCES AT ALL UTILITY CROSSINGS. CUT AND CAP |
| | UTILITIES NOT IN USE, AND REMOVE ANY ABANDONED UTILITY |
| | LINES LARGER THAN 2 INCHES FROM CITY RIGHT OF WAY. |
| | |
| | 3. PLEASE SUBMIT COMPLETED LOS ANALYSIS SUMMARY TABLE |
| | DIRECTLY TO ENGINEERING (SHEET 33 OF CITY OF WPB |
| | DEVELOPMENT APPLICATION). |
| | |
| | 4. PROVIDE CALCULATIONS ON PLANS OF EXISTING AND |
| | PROPOSED DEMANDS FOR WATER & SEWER (AVERAGE, MAXIMUM |
| | AND PEAK) AND FIRE FLOW DEMANDS. CALCULATIONS SHALL BE |
| | PER FAC 64E-6 FOR SEWER AND PER FAC 64-E.008 FOR WATER. |
| | |
| | 5. PROVIDE CCTV VIDEO OF EXISTING SANITARY SEWER ALONG |
| | ENTIRE PROJECT FRONTAGE. |
| | |
| | 6. CHECK TO SEE IF FDEP FORMS FOR PROPOSED SANITARY |
| | SEWER ARE REQUIRED. |
| | |
| | ---THE FOLLOWING COMMENTS ARE FOR THE FORMAL |
| | ENGINEERING SUBMITTAL:--- |
| | |
| | 7. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE |
| | EASEMENT FOR PLACEMENT OF PROPOSED WATER METERS. |
| | |
| | 8. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE |
| | ENLARGED VIEW ON PLANS OF PROPOSED LOCATION OF WATER |
| | METER AND BACKFLOW PREVENTION. |
| | |
| | 9. FOR FORMAL ENGINEERING SUBMITTAL, PROVIDE PROFILES |
| | OF WATER AND SEWER AND SHOW ANY CROSSINGS/CONFLICTS. |
| | |
| | 10. FOR FORMAL ENGINEERING SUBMITTAL, WHEN SUBMITTING |
| | APPROVED MATERIALS LIST, PLEASE PROVIDE MATERIAL/CUT |
| | SHEETS FOR ALL PROPOSED BACKFLOW DEVICES SHOWING |
| | SPECIFIC MODEL NUMBER AND SPECIFYING USC APPROVED |
| | LEAD-FREE DESIGN. |
| | |
| | 11. FOR FORMAL ENGINEERING SUBMITTAL, IF SANITARY LINES |
| | ARE PROPOSED IN ROW PLEASE SHOW ADJACENT SANITARY |
| | LATERAL LOCATIONS AND SHOW ADDRESSES OF ADJACENT |
| | PARCELS. |
| | |
| | 12. FOR FORMAL ENGINEERING SUBMITTAL, IF WATER LINES |
| | ARE BEING REPLACED IN ROW, SHOW ADJACENT PARCEL |
| | ADDRESSES. |
| | |
| | 13. FOR FORMAL ENGINEERING SUBMITTAL, ADD NOTE TO |
| | PROVIDE 50 FT. PAVEMENT RESTORATION TRANSITION ON EACH |
| | SIDE OF PROPOSED TRENCH IN CITY MAINTAINED ROADWAY |
| | AREAS PER CITY OF WPB STANDARD DETAIL GC-9. |
| | |
| | 14. FOR FORMAL ENGINEERING SUBMITTAL, SHOW DIMENSIONS |
| | OF PROPOSED DUMPSTER PER CURRENT CITY OF WPB STANDARD |
| | DETAIL GC-8. |
| | |
| | 15. FOR FORMAL ENGINEERING SUBMITTAL, PLEASE PROVIDE |
| | CALCULATIONS OF PERVIOUS AND IMPERVIOUS AREAS FOR |
| | PROPOSED IMPROVED AREAS. |
| | |
| | |
| | FEEL FREE TO CONTACT US IF YOU HAVE ANY QUESTIONS OR |
| | CONCERNS, THANKS. |
| | |
| | RICK ROSSANO |
| | PROJECT COORDINATOR |
| | ENGINEERING SERVICES DEPARTMENT |
| | 401 CLEMATIS STREET, 4TH FLOOR |
| | WEST PALM BEACH, FL 33401 |
| | (MAILING ADDRESS: P.O. BOX 3366, ZIP 33402) |
| | DIRECT: (561) 494-1098 |
| | FAX: (561) 494-1116 |
| | MOBILE: (561) 246-9525 |
| | EMAIL: [email protected] |
| | WWW.WPB.ORG/ENGINEERING |
| | |
| | |
| |