| Date |
Text |
| 2019-05-07 18:25:49 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT |
| | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR |
| | MS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY?S VERTICAL DATUM IS NGVD 1929. THE CITY HAS |
| | ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION |
| | EQUATION TO NGVD 1929 IS PROVIDED ON THE SHEET(S). |
| | PROVIDE NAVD1988 TO NGVD1929 CONVERSION EQUATION ON THE |
| | ENGINEERING PLANS. |
| | |
| | 2. END OF PAVERS IN THE ALLEY DO NOT ALIGN WITH THE |
| | EXISTING ASPHALT ROADWAY. |
| | |
| | 3. CHECK SIDEWALK SLOPE BETWEEN NEW APARTMENTS AND BACK |
| | OF SIDEWALKS ON ALPHA ST. AND MERCER ST. STEPS MAY BE |
| | REQUIRED. |
| | |
| | 4. SHOW MILLING AND RESURFACING LIMITS FOR PAVEMENT |
| | CUTS IN THE RIGHT-OF-WAY. |
| | |
| | 5. PIPE BETWEEN STRUCTURES S-204 AND S-102 MISLABELED |
| | AS OUTFALL. |
| | |
| | 6. SHOW DRAINAGE FLOW ARROWS FOR SURFACE RUNOFF ON THE |
| | CONCEPTUAL PG&D PLAN. |
| | |
| | 7. PROVIDE WATER QUALITY TREATMENT FOR THE PROPOSED |
| | PARKING SPACES ON ALPHA ST. |
| | |
| | 8. PROVIDE CCTV OF THE STORMWATER PIPES IN MERCER AVE. |
| | |
| | 9. TRANSFER WATER SERVICES ON EXISTING WATER MAIN TO |
| | NEW WATER MAIN ON ALPHA ST. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP PERMIT PRIOR TO |
| | STARTING CONSTRUCTION. |
| | |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |
Print |