| 2019-02-15 10:25:58 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR |
| | MS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. ADD NAVD1988 TO NGVD 1929 CONVERSION EQUATION TO |
| | SURVEY. |
| | |
| | 2. ADD VERTICAL DATUM AND CONVERSION EQUATION TO |
| | NGVD1929 TO SHEET 2 OF 6. |
| | |
| | 3. LIST VERTICAL DATUM AND CONVERSION TO NGVD1929 TO |
| | ALL SHEETS THAT LIST ELEVATION DATA. |
| | |
| | 4. STORM OUTFALL CANNOT CONNECT TO THE SCHOOL DISTRICT |
| | STORM PIPE. |
| | |
| | 5. ROEBUCK ROAD IS MAINTAINED BY PALM BEACH COUNTY. |
| | |
| | 6. LANDSCAPE PLANS: |
| | A. TREE PROPOSED OVER SANITARY LATERAL |
| | B. WILL EXISTING PALM TREES BE IMPACTED BY THE |
| | INSTALLATION OF THE SANITARY SEWER MAIN. |
| | C. CYPRESS TREES PROPOSED ON SIDE SLOPE OF STORMWATER |
| | DETENTION POND. |
| | |
| | 7. LABEL THE CONTOURS OF THE STORMWATER POND. |
| | |
| | 8. PERVIOUS PAVERS WILL BE CONSIDERED AS IMPERVIOUS |
| | AREA. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP APPROVAL PRIOR TO |
| | STARTING CONSTRUCTION. |
| | |
| | 4. PROVIDE A COPY OF NPBCID PERMIT BEFORE THE START OF |
| | CONSTRUCTION. |
| | |
| |