| Date |
Text |
| 2019-02-05 14:27:26 | 3RD REVIEW RESPONSE |
| | |
| | |
| | AFTER A REVIEW OF THE PPRC INFORMATION PACKET AND |
| | RESPONSE LETTER DATED FEBRUARY 4, 2019, FROM HEATHER |
| | DANFORTH, SENIOR PLANNER, THE PREVIOUSLY SUBMITTED FIRE |
| | PREVENTION BUREAU COMMENTS HAVE BEEN ADDRESSED. |
| | |
| | HOWEVER, THE LOCATION AND DELINEATION OF A DEFINITIVE |
| | FIRE LANE WAS NOT CLEARLY INDICATED OF THE SUBMITTED |
| | PLAN. ADDITIONAL COMMUNICATION WITH THE OFFICE OF THE |
| | FIRE MARSHAL IS STRONGLY ENCOURAGED TO AVOID |
| | CONSTRUCTION DELAYS OR UNNECESSARY WORK. I HAVE |
| | COMMUNICATED BY EMAIL WITH TODD MCLEOD, P.E., ON THIS |
| | ISSUE TO MOVE THIS PROJECT FORWARD AND WORK THE |
| | SPECIFIC LOCATIONS COLLECTIVELY BEFORE CONSTRUCTION. |
| | |
| | ADDITIONALLY, IT WAS BROUGHT TO MY ATTENTION THAT THE |
| | FIRE HYDRANT NEAR THE PARK AREA IS IN NEED OF |
| | RELOCATION. THE RELOCATION OF THE FIRE HYDRANT SHOWN ON |
| | THE REVISED CIVIL IS ACCEPTABLE. THE LOCATION OF THE |
| | REVISED FDC/DDCV IN THE PARK IS NOT AND NEEDS TO BE |
| | RELOCATED COLLECTIVELY AS NOTED ABOVE. |
| | |
| | THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT DOES |
| | NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL. |
| | |
| | THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING PLANS AT |
| | THE APPROPRIATE TIME AND IN ACCORDANCE WITH THE |
| | REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS. |
| | |
| | |
| | PETER LEDUC |
| | FIRE MARSHAL |
| | WEST PALM BEACH FIRE RESCUE |
| | 561-804-4709 |
| | [email protected] |
| |