Plan Review Notes
Plan Review Notes For Project Z18110018
Project Number Z18110018
Review Stop STORM
Sequence Number 1
Notes
Date Text
2018-12-11 08:22:02THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT:
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. LIST THE VERTICAL DATUM ON THE ENGINEERING PLANS.
 THE CITY VERTICAL DATUM IS NGVD 1929. THE CITY HAS
 ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION
 EQUATION TO NGVD 1929 IS PROVIDED.
  
 2. THE NAVD1988 / NGVD1929 CONVERSION EQUATION IS
 NEEDED ON THE SURVEY.
  
 3. BROADWAY AVE. IS MAINTAINED BY FDOT. PERMITS WILL BE
 NEEDED FROM FDOT ANY WORK IN THE BROADWAY AVE.
 RIGHT-OF-WAY.
  
 4. ON THE SWPPP, SHOW PROTECTION FOR THE INLET ON
 BROADWAY BLVD.
  
 5. SHOW THE MILL AND RESURFACING LIMITS OF CWPB RIGHTS
 OF WAY. SEE CWPB?S STANDARD DETAIL GC-9 TO DETERMINE
 THE LIMITS.
  
 6. SIDEWALK EASEMENTS MAY BE NEEDED FOR SIDEWALKS ALONG
 27TH ST. AND 28TH ST.
  
 7. SHOW UTILITIES ON THE LANDSCAPE PLANS.
  
 8. SHOW ROOT BARRIERS NEXT TO UTILITY PIPES.
  
 9. SUGGEST REDUCING IMPERVIOUS AREA AND USING PERVIOUS
 PAVERS AROUND PERIMETER OF SITE TO REDUCE THE AMOUNT OF
 RUNOFF FLOWING UNCONTROLLED INTO THE PUBLIC
 RIGHTS-OF-WAY.
  
 10. VERIFY A FDOT TYPE ?V? INLET TOP WILL FIT ON
 STRUCTURES DS-28 AND DS-29.
  
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 3. PROVIDE A COPY OF THE SFWMD ERP APPROVAL PRIOR TO
 STARTING CONSTRUCTION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120