| 2018-12-11 08:44:31 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT: |
| | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR |
| | MS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. LABEL THE VERTICAL DATUM ON THE ENGINEERING PLANS. |
| | |
| | 2. UPDATE THE FEMA FIRM INFORMATION ON THE BOUNDARY |
| | SURVEY. NEW FIRMS WERE ISSUED IN 2017. BECAUSE THE |
| | VERTICAL DATUM ON THE SURVEY IS NGVD1929 AND ON THE NEW |
| | FIRMS IS NAVD1988, THE CONVERSION BETWEEN NAVD1988 AND |
| | NGVD1929 WILL NEED TO BE SHOWN ON THE SURVEY. |
| | |
| | 3. SHOW PROPOSED UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. PROVIDE SFWMD ERP MODIFICATION FOR THE DEVELOPMENT. |
| | |
| | 3. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |