| 2018-09-12 07:45:31 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY VERTICAL DATUM IS NGVD 1929. THE CITY HAS |
| | ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION |
| | EQUATION TO NGVD 1929 IS PROVIDED. THE CONVERSION |
| | EQUATION IS NEEDED ON THE SURVEY. |
| | |
| | 2. MOVE DRAINAGE STRUCTURE S-101 OUT OF THE |
| | RIGHT-OF-WAY FOR PEMBROKE PLACE. |
| | |
| | 3. INDICATE IF THERE IS A DRAINAGE EASEMENT FOR THE |
| | STORM PIPE CROSSING THE PROPERTY TO THE NORTH. |
| | |
| | 4. INDICATE THE CURB CUT ON DIXIE HIGHWAY WILL BE |
| | REMOVED AND THE SIDEWALK ALONG THE CURB CUT WILL BE |
| | REPLACED. |
| | |
| | 5. INDICATE ON THE ENGINEERING PLANS THE LIMITS OF |
| | CONSTRUCTION ON PEMBROKE PLACE INCLUDING MILLING AND |
| | RESURFACING LIMITS. |
| | |
| | 6. REVIEW THE CONSTRUCTABILITY OF MAKING FUTURE REPAIRS |
| | OR REPLACEMENT OF THE STORM PIPE OR EXFILTRATION TRENCH |
| | WITH THEIR PROXIMITY TO THE BUILDING. |
| | |
| | 7. THE PROPOSED SITE PLAN APPEARS TO BE MISALIGNED ON |
| | THE CONCEPTUAL ENGINEERING PLANS. |
| | |
| | 8. PROVIDE VALLEY GUTTER BETWEEN DROP AREA AND TRAVEL |
| | LANE ON PEMBROKE PLACE. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE A COPY OF THE MODIFIED SFWMD ERP APPROVAL |
| | PRIOR TO STARTING CONSTRUCTION. |
| | |
| | 4. SOUTH DIXIE HIGHWAY IS MAINTAINED BY FLORIDA |
| | DEPARTMENT OF TRANSPORTATION. PROVIDE A COPY OF FDOT |
| | APPROVAL FOR ALL WORK PROPOSED WITHIN THE DIXIE HWY |
| | RIGHT-OF-WAY. |
| | |
| | 5. PROVIDE FDOT APPROVAL FOR DRAINAGE CONNECTION TO THE |
| | ROADWAY DRAINAGE SYSTEM. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |