| Date |
Text |
| 2018-08-07 11:37:16 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT HTTP://WPB.ORG/DEPARTMENTS/ENGINEE |
| | RING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE CITY VERTICAL DATUM IS NGVD 1929. THE CITY HAS |
| | ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION |
| | EQUATION TO NGVD 1929 IS PROVIDED. |
| | |
| | 2. THE VERTICAL DATUM USED SHALL BE CONSISTENT BETWEEN |
| | ALL PLANS. THE MAPS OF BOUNDARY SURVEY ARE REFERENCING |
| | NGVD 1929. THE ENGINEERING PLANS REFERENCE NAVD 1988. |
| | |
| | 3. UPDATE THE FLOOD ZONE INFORMATION ON THE MAPS OF |
| | BOUNDARY SURVEY. NEW FIRMS WERE ISSUED IN 2017. LIST |
| | THE DATE OF THE FIRM PANEL MAP. |
| | |
| | 4. WHAT IS PLANNED FOR THE EXISTING UTILITY POLE AND |
| | GUY WIRES IN THE MIDDLE OF THE EXISTING DRIVEWAY ON LOT |
| | 12? |
| | |
| | 5. THE ONSITE DRAINAGE SYSTEM IS TO BE DESIGNED TO MEET |
| | SFWMD CRITERIA FOR WATER QUALITY TREATMENT AND OFFSITE |
| | DISCHARGES. |
| | |
| | 6. OFFSITE IMPROVEMENTS IN THE PUBLIC RIGHT OF WAY TO |
| | BE DESIGN AND CONSTRUCTED IN ACCORDANCE WITH CITY |
| | STANDARDS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | 3. PROVIDE SFWMD ERP FOR THE DEVELOPMENT. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |
Print |