| 2018-10-01 16:53:12 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 |
| | PROJECT: PEGGY ADAMS Z18060025 |
| | OCTOBER 1, 2018 |
| | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND |
| | PROVIDE THE FOLLOWING COMMENTS: |
| | |
| | 1. PREVIOUSLY SATISFIED. |
| | 2. SATISFIED. UPDATE THE FLORIDA FRIENDLY LANDSCAPE |
| | DESIGN OPTIONS CHART TO CURRENT CODE SECTION 94-446 (G) |
| | AND PROVIDE 50 POINTS AS REQUIRED. |
| | CORRECT THE FOLLOWING: |
| | ? #8 MULCH IS ONLY 5 POTENTIAL POINTS. |
| | ? #3 CANNOT COUNT 51% NATIVE AND 51% DROUGHT TOLERANT. |
| | ? NOTE SHOULD READ: PLANTS MAY ONLY BE COUNTED ONCE FOR |
| | CREDIT TOWARD DROUGHT TOLERANT OR FLORIDA NATIVE |
| | PLANTS. |
| | |
| | 3. PREVIOUSLY SATISFIED. |
| | |
| | 4. SATISFIED. PLEASE PROVIDE THE REQUIRED TREES IN THE |
| | TWO TERMINAL LANDSCAPE ISLANDS IN THE ROW OF PARKING |
| | ADJACENT TO THE ENTRANCE TO THE NEW BUILDING, AND THE |
| | TWO TERMINAL ISLANDS AT THE NORTH END OF THE PARKING |
| | ROWS WEST OF THE DOME BUILDING. NON-CONFORMING PARKING |
| | ROW ON THE NORTH SIDE OF THE NEW BUILDING MAY ALSO HAVE |
| | TREES ADDED IN TERMINAL ISLANDS. ANY MODIFICATIONS TO |
| | ANY PARKING AREAS REQUIRES COMPLIANCE WITH CURRENT |
| | CODE. |
| | |
| | LANDSCAPE ISLANDS ADJACENT TO THE NEW BUILDING AND AT |
| | THE SOUTHEAST CORNER OF THE DOME BUILDING ARE SHOWN |
| | WITH SINGLE ALEXANDER PALMS THAT DO NOT MEET THE CODE |
| | REQUIREMENT. THERE IS SUFFICIENT PLANTING AREA TO |
| | INSTALL ROOT BARRIERS TO PROTECT THE LINES AND ADD THE |
| | REQUIRED TREE. |
| | |
| | 5. PREVIOUSLY SATISFIED. |
| | |
| | 6. SATISFIED. THE REMOVAL AND MITIGATION OF TREES FOR |
| | THE DRAINAGE AREA RELOCATION WAS APPROVED WITH A TREE |
| | ALTERATION PERMIT. A LANDSCAPE PERMIT WAS NOT APPLIED |
| | FOR OR ISSUED FOR THE INSTALLATION OF THE NEW TREES. A |
| | LANDSCAPE PERMIT WITH AN AS BUILT PLAN MUST BE |
| | SUBMITTED FOR THE NEW DRAINAGE AREA TO CONFIRM THAT ALL |
| | REQUIRED MITIGATION HAS BEEN COMPLETED. |
| | |
| | A LANDSCAPE PERMIT WAS SUBMITTED, REVIEWED AND APPROVED |
| | AS THE AS BUILT, BUT I WAS INFORMED IS NOT ACCURATE TO |
| | THE AS BUILT PRIOR TO IT BEING ISSUED. THE CORRECTED |
| | PLAN MUST BE SUBMITTED, REVIEWED, APPROVED AND |
| | INSPECTED TO VERIFY IT IS ACCURATE. AT THAT TIME THE |
| | PLAN CAN BE INCLUDED WITH THE SUBMITTAL PLAN SET WITH |
| | ANY CORRECTIONS MADE TO THE OVERALL SITE CALCULATIONS. |
| | |
| | 7. PREVIOUSLY SATISFIED. |
| | |
| | 8. PREVIOUSLY SATISFIED. |
| | 9. PREVIOUSLY SATISFIED. |
| | |
| | 10. SATISFIED. PLEASE SUPPLY A COMPREHENSIVE LANDSCAPE |
| | PLAN FOR THE SITE, WITH AN ACCOUNTING OF THE TREES ON |
| | SITE AND INCLUDE ALL CURRENTLY APPROVED PLANS SO THAT |
| | STAFF CAN EVALUATE THE COMPARISON BETWEEN THE OVERALL |
| | REQUIRED TREES AS APPROVED WITH THE CSPD AND WHAT IS |
| | PROPOSED FOR THE FINAL DESIGN. |
| | |
| | SEE COMMENT #6. |
| | |
| | ADDITIONAL COMMENTS 8/20/18: |
| | 11. SATISFIED. TEMPORARY TRAILERS DETAIL INCLUDES TREES |
| | AND HEDGE. IF TREES AND HEDGE ARE TO STAY AFTER TRAILER |
| | REMOVAL, SHOW IT ON SHEET LP-2 AS PERMANENT. THE 4 CE2 |
| | ARE CURRENTLY COUNTED TOWARD SITE TREE CREDITS ON THE |
| | PLANT LIST. |
| | |
| | 12. SATISFIED. SHOW THE TREES AND SHRUBS IN THE BUFFER |
| | ALONG MILITARY TRAIL ON SHEET LP-2 THAT ARE WITHIN THE |
| | LIMITS OF AFFECTED AREA. THEY CAN BE NOTED AS APPROVED |
| | AS SHOWN ON OTHER SHEETS, BUT THE BUFFER MUST BE SHOWN |
| | ACCURATELY FOR THE NEW BUILDING. |
| | |
| | 13. SATISFIED. SHOW THE BUFFER HEDGE ALONG THE NORTH |
| | PROPERTY LINE FOR ALL AREAS NOT SUBJECT TO THE WAIVER |
| | REQUEST, AS THERE ARE PORTIONS NOT SHOWN ON THE |
| | SUBMITTED PLANS. |
| | CONDITIONS OF APPROVAL |
| | 1. PRIOR TO SCHEDULING FOR PLANNING BOARD, THE |
| | APPLICANT SHALL REVISE THE LANDSCAPE PLAN TO SHOW THE |
| | ROOT BARRIERS SPACED CLOSER TO THE DRAINAGE LINES TO |
| | PROTECT THE PRIVATE LINES YET ALLOW FOR ADEQUATE ROOT |
| | DEVELOPMENT OF THE TREES. |
| | |
| | 2. PRIOR TO SCHEDULING FOR PLANNING BOARD, THE |
| | APPLICANT SHALL REVISE THE LANDSCAPE PLAN TO SHOW THE |
| | REQUIRED HEDGE IN THE WEST BUFFER FOR ALL AREAS NORTH |
| | OF THE EXISTING HEDGE. |
| | |
| | 3. PRIOR TO SCHEDULING FOR PLANNING BOARD, THE |
| | APPLICANT SHALL REVISE THE LANDSCAPE PLAN FOR THE POND |
| | AREA TO REFLECT ANY CHANGES DISCOVERED DURING THE |
| | LANDSCAPE INSPECTION. |
| | |
| | 4. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON |
| | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE |
| | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT |
| | SERVICES DEPARTMENT, PLANNING DIVISION. |
| | |
| |