2018-08-08 15:56:09THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE
 AUGUST 3, 2018 REVIEW PACKAGE:
  
 1. PROVIDE A TYPICAL CROSS SECTION FROM THE SOUTH
 PROPERTY LINE THROUGH THE NEW PARKING LOTS SOUTH OF THE
 TWO-STORY DOME BUILDING. IT DOESN'T APPEAR A SWALE WITH
 3:1 SLOPES CAN BE CONSTRUCTED ALONG THE SOUTH PROPERTY
 LINE UNLESS THERE IS A RETAINING WALL ALONG THE SOUTH
 EDGE OF THE PARKING.
  
 2. REVIEW THE GRADING OF THE EAST END OF THE PARKING
 LOT SOUTH OF THE TWO-STORY DOME BUILDING. THERE IS A
 PAVEMENT GRADE OF 18.53 FT NGVD IN THE CORNER OF THE
 PARKING LOT. THE NEAREST CATCH BASIN TO THE NORTH WILL
 HAVE A GRATE ELEVATION OF 18.70 FT NGVD.
  
 3. REVIEW THE UTILITY CONFLICT SEPARATION NOTES ON THE
 UTILITY PLAN. THE NOTES ARE WRITTEN TO MAKE IT APPEAR
 THE FIRE LINES WILL BE CONSTRUCTED UNDER THE STORM
 PIPES FOR EXAMPLE, THE WATER LINE TO THE FIRE HYDRANT
 AND TO THE FDC, THE CONFLICT IS WRITTEN AS STORM BOP
 AND FIRE TOP. IF THE WATER LINES ARE PASSING UNDER THE
 STORM THEN 12" OF CLEARANCE WILL BE REQUIRED INSTEAD OF
 6".
  
 4. DRAINAGE STRUCTURE ST-1 IS REPLACING AN EXISTING
 STRUCTURE. IS THE EXISTING STRUCTURE A CONTROL
 STRUCTURE FOR THE LAKE TO THE SOUTH OF THE ENTRANCE
 ROAD?
  
 TRACY L. WARD, P.E.
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved