| Plan Review Notes For Project Z18050032 |
| Project Number |
Z18050032 |
|
| Review Stop |
STORM |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2018-08-24 14:05:38 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE | | | AUGUST 22, 2018 SUBMITTAL PACKAGE: | | | 1. ADD THE NAVD TO NGVD CONVERSION EQUATION TO THE 21 | | | PAGE SURVEY PACKAGE. | | | | | | 2. REVISE THE SCALE BAR ON SHEET EXH1. I BELIEVE THE | | | SCALE SHOULD BE 1 INCH = 40 FEET. | | | | | | 3. DESIGN THE LANDSCAPE STRIPS DEEP ENOUGH FOR WATER TO | | | FLOW AROUND THE PROPOSED TREES AND NOT BACK UP ONTO THE | | | PARKING LOT. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | [email protected] | | | 561-494-1120 |
| |