| Date |
Text |
| 2020-01-09 10:26:12 | 1. WILL NEED TO SEE HOW THE BRIDGE OVER THE UTILITIES | | | IS DESIGNED. | | | 2. PROPERTY WILL NEED TO BE REPLATTED PRIOR TO C.O. | | | 3. AS OF 1/9/2020, CCTV HAS NOT BEEN RECEIVED. | | | 4. PERMIT FROM FEC WILL BE REQUIRED FOR CONNECTION TO | | | EXISTING DRAINAGE IN RIGHT-OF-WAY. APPROVAL WILL BE | | | NEEDED FROM TRACY WARD, STORMWATER ENGINEER. POST CCTV | | | WILL ALSO BE REQUIRED. CONSIDER CONNECTING BISCAYNE | | | DRAINAGE THRU SITE TO FLAMINGO INSTEAD OF FEC. | | | 5. ABANDONMENT OF BISCAYNE WILL NEED TO BE FINALIZED. | | | |
| |