| 2018-05-09 14:49:30 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. THE PROPOSED STORM PIPE FROM THE INLET ON THE SOUTH |
| | SIDE OF BISCAYNE ROAD APPEARS TO CROSS THE ADJOINING |
| | PROPERTY. THE PIPE SHOULD BE WITHIN THE RIGHT-OF-WAY |
| | AND/OR APPLICANT?S PROPERTY WITHOUT THE NEED FOR A |
| | CONSTRUCTION EASEMENT. |
| | |
| | 2. THE PROPOSED MANHOLE AND STORM PIPE ON FLAMINGO DR. |
| | NEEDS TO BE RELOCATED TO OUTSIDE THE RIGHT-OF-WAY. IT |
| | ONLY CONVEYS STORMWATER RUNOFF FROM THE APPLICANT?S |
| | PROPERTY. |
| | |
| | 3. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | 4. ONSITE DRAINAGE SYSTEM TO PROVIDE FOR WATER QUALITY |
| | TREATMENT AND PEAK FLOW LIMITATION PER SFWMD CRITERIA |
| | FOR RUNOFF FROM THE PROJECT SITE. |
| | |
| | 5. PERMIT WILL BE NEEDED TO WORK WITHIN THE F.E.C. |
| | RIGHT-OF-WAY. |
| | |
| | 6. 2017 FEMA FIRM MAPS AND TWO FEET OF FREEBOARD ABOVE |
| | BASE FLOOD ELEVATION FOR STRUCTURES IN SPECIAL FLOOD |
| | HAZARD AREA ARE NOW IN EFFECT. THE MAPS ARE AVAILABLE |
| | AT HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX? |
| | UPDATE THE FLOOD ZONE INFORMATION ON THE BOUNDARY |
| | SURVEY. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED |
| | WITH THE ENGINEERING PERMIT APPLICATION. |
| | |
| | |
| | 3. PROVIDE SFWMD ERP FOR THE DEVELOPMENT. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |