Plan Review Notes
Plan Review Notes For Project Z18010013
Project Number Z18010013
Review Stop STORM
Sequence Number 2
Notes
Date Text
2018-04-18 18:01:11THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE APRIL
 12, 2018 REVIEW PACKAGE FROM THE PLANNER:
  
 1. VERTICAL DATUM ON THE SURVEY AND ENGINEERING PLANS
 NEEDS TO BE CONSISTANT. ELEVATIONS ON THE SURVEY ARE
 INDICATED TO BE IN REFERENCE TO NAVD 1988. ELEVATIONS
 ON THE ENGINEERING PLANS ARE INDICATED TO BE IN
 REFERENCE TO NGVD 1929. EXISTING SPOT GRADE VALUES ARE
 THE SAME ON THE SURVEY AND ENGINEERING PLANS.
  
 2. THE CONVERSION (DIFFERENCE) BETWEEN NAVD 1988 AND
 NGVD 1929 VERTICAL DATUMS LISTED ON THE SURVEY AND ON
 THE ENGINEERING PLANS NEEDS TO BE CONSISTANT. ONE USES
 1.52 FEET AND THE OTHER USES 1.53 FEET.
  
 3. SHEET C4.00 LISTS THE FINISHED FLOOR ELEVATION AS
 12.00 FEET NGVD. SHEET A1.0 LISTS THE FINISHED FLOOR
 ELEVATION AS 12 FT 6 INCHES.NGVD.
  
 4. SHEET C4.00 SHOWS ONSITE CONCRETE STEPS ALONG THE
 NORTH SIDE OF THE ALLEY ACROSS THE DRIVEWAY TO THE
 TRASH / GAS '/ GENERATOR ROOM AND OUTSIDE THE DOOR TO
 THE STAIRWELL AT THE EAST END OF THE ALLEY. NEITHER
 SETS OF STEPS ARE SHOWN ON THE SITE PLAN (SHEET A1.0).
 INDICATE HOW THE TRASH BE HANDLED IF THERE ARE STEPS IN
 THIS LOCATION. CAN THE BOTTOM FLOOR OF THE STAIRWELL BE
 TAKEN DOWN TO THE ELEVATION OF THE ALLEY SO STEPS WILL
 NOT BE NEEDED OUTSIDE THE DOOR?
  
 5. PROVIDE DETAIL OF THE EXFILTRATION TRENCH INCLUDING
 WIDTH AND TOP ELEVATION OF THE TRENCH.
  
 6. PROVIDE THE WEIR ELEVATION FOR STRUCTURE ST-01.
  
 7. MINIMUM 15" RCP STORM PIPE WITHIN THE PUBLIC
 RIGHT-OF-WAY.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  
  
  
  