Plan Review Notes
Plan Review Notes For Project Z18010012
Project Number Z18010012
Review Stop STORM
Sequence Number 1
Notes
Date Text
2018-02-14 12:57:54THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. PHOTOMETRIC PLAN EPH-1.1 MISLABELED.
  
 2. REVISE FIRE HYDRANT CLEAR ZONE DETAIL THE LANDSCAPE
 PLANS. SEE CITY DETAIL P-8 (AVAILABLE ONLINE).
  
 3. LANDSCAPE PLANS LABEL WATER AND STORM UTILITIES AS
 EASEMENTS.
  
 4. UPDATE LIST OF PROFESSIONAL FIRMS ON ARCHITECTURAL
 INDEX OF DRAWINGS PAGE.
  
 5. THE CITY VERTICAL DATUM IS NGVD 1929. THE CITY HAS
 ALLOWED THE USE OF NAVD 1988 PROVIDED THE CONVERSION
 EQUATION TO NGVD 1929 IS PROVIDED.
  
 6. VERTICAL DATUM INCONSISTENT ON THE CIVIL PLANS. NOTE
 ON SHEET C1.01 LISTS VERTICAL DATUM AS NGVD 1929. OTHER
 CIVIL SHEETS AND THE TOPOGRAPHIC SURVEY LIST THE
 VERTICAL DATUM AS NAVD 1988.
  
 7. WILL A SIDEWALK EASEMENT ON HAMPTON ROAD BE
 PROVIDED?
  
 8. DRIVEWAY FLARES DO NOT MATCH CITY STANDARD DETAILS
 GC-6 OR GC-7.
  
 9. DRAINAGE FLOW ARROWS FOR THE SOUTH PARKING LOT DO
 NOT AGREE WITH THE PROPOSED GRADES.
  
 10. PARKING AND DRIVE AISLE CROSS SLOPES APPEAR TO BE
 CLOSE TO 8% WEST OF BUILDING 4 AND CLOSE TO 5% EAST OF
 BUILDING 4.
  
 11. ADD SPOT GRADES IN THE DRIVE AISLE IN THE NORTH
 PARKING LOT TO INDICATE INVERTED CROWN SECTION.
  
 12. CONSIDER ADDING CROSS SECTIONS FROM PROPERTY LINE
 TO PROPERTY LINE TO INDICATE MAX./MIN.
 PAVEMENT/SIDEWALK SLOPES AND TIES TO THE FFE.
  
 13. FOUNTAIN DRAIN MAY NOT BE ABLE TO BE CONNECTED TO
 THE STORM DRAIN SYSTEM.
  
 14. PAVEMENT STRIPING PLAN WILL BE NEEDED FOR HAMPTON
 ROAD.
  
 15. ROOF DRAINS SHOULD CONNECT TO DRAINAGE SYSTEM
 INSTEAD OF SURFACE DISCHARGE.
  
 16. JUSTIFICATION STATEMENT INDICATED RIGHT-OF-WAY
 DEDICATION FOR HAMPTON ROAD. SHOW THE LIMITS ON THE
 PLANS.
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. EROSION CONTROL PLAN AND DETAILS TO BE SUBMITTED
 WITH THE ENGINEERING PERMIT APPLICATION.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  