2018-01-09 14:36:26THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. NEW FEMA FIRM MAPS AND TWO FEET OF FREEBOARD ABOVE
 BASE FLOOD ELEVATION FOR STRUCTURES IN SPECIAL FLOOD
 HAZARD AREA ARE NOW IN EFFECT. THE MAPS ARE AVAILABLE
 AT HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX?
  
 2. UPDATE THE FLOOD ZONE INFORMATION ON THE SURVEY.
  
 3. CONFLICTING VERTICAL DATUMS: BOUNDARY AND
 TOPOGRAPHIC SURVEY LISTS THE VERTICAL DATUM AS NAVD
 1988. CONCEPTUAL WATER AND WASTEWATER PLAN LISTS THE
 VERTICAL DATUM AS NGVD 1929. PER SECTION 78-9 OF THE
 CODE OF ORDINANCES, THE VERTICAL DATUM FOR THE CITY IS
 NGVD 1929. THE CITY HAS BEEN ALLOWING THE USE OF NAVD
 1988 PROVIDED THE CONVERSION BETWEEN NGVD AND NAVD IS
 PROVIDED ON THE SURVEY/PLANS.
  
 4. LABEL VERTICAL DATUM ON CONCEPTUAL PAVING, GRADING &
 DRAINAGE PLAN.
  
 5. SHOW PAVEMENT MILL AND OVERLAY LIMITS FOR THE TRENCH
 REPAIR PER CITY DETAIL GC-9.
  
 6. RCP PIPE TO BE USED IN PUBLIC RIGHT-OF-WAY.
  
 7. THERE IS A 12? FM ON MERCER AVE BETWEEN THE 6? WM
 AND SANITARY SEWER MAIN.
  
 8. VERIFY THERE IS SUFFICIENT SPACE FOR THE LANDING AT
 THE PROPOSED CURB RAMP AT THE NORTHWEST CORNER OF
 MERCER AVE AND ALPHA STREET.
  
 9. WHAT ARE THE INSIDE DIMENSIONS OF THE TYPE ?C-D?
 STRUCTURES? CAN TWO PRB?S BE INSTALLED IN THEM
 (ADJACENT SIDES IN STRUCTURE S-102; OPPOSITE SIDES IN
 STRUCTURE S-103)?
  
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. INCLUDE CITY STANDARD DETAILS FOR WORK WITHIN THE
 RIGHT-OF-WAY.
  
 3. THE PRELIMINARY STORMWATER CALCULATIONS LABEL THE
 SFWMD DRAINAGE BASIN AS INTRACOASTAL. THE RUNOFF FROM
 THE PROJECT ULTIMATELY DISCHARGES THROUGH THE CONTROL
 STRUCTURE FOR THE C-51 CANAL. THE MERCER AVE DRAINAGE
 SYSTEM OUTFALLS INTO THE STUBB CANAL, SOUTH OF THE BOYD
 STREET DIVIDE STRUCTURE. THE STUBB CANAL IS UPSTREAM OF
 THE C-51 CANAL CONTROL STRUCTURE. INCLUDE CALCULATIONS
 DEMONSTRATING THE PROJECT MEETS THE C-51 BASIN RULES
 FOR PEAK DISCHARGE AND FLOOD PLAIN STORAGE.
  
 4. VERTICAL DATUM LISTED IN THE STORMWATER CALCULATIONS
 NEEDS TO MATCH THE VERTICAL DATUM USED FOR THE CIVIL
 PLANS.
  
 5. PROVIDE SITE SPECIFIC EXFILTRATION TEST RESULTS.
  