| 2018-01-09 14:27:33 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. NO ENGINEERING PLANS WERE PROVIDED. |
| | |
| | 2. LABEL VERTICAL DATUM ON THE SITE PLAN. |
| | |
| | 3. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | 4. PROVIDE DRAINAGE IMPROVEMENTS FOR THE CURB RAMP AT |
| | THE NE CORNER OF TAMARIND AVE AND 20TH ST. |
| | |
| | 5. NEW FEMA FIRM MAPS AND TWO FEET OF FREEBOARD ABOVE |
| | BASE FLOOD ELEVATION FOR STRUCTURES IN SPECIAL FLOOD |
| | HAZARD AREA ARE NOW IN EFFECT. THE MAPS ARE AVAILABLE |
| | AT HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX? |
| | |
| | 6. UPDATE FLOOD ZONE INFORMATION (NOTE NO. 9) ON THE |
| | BOUNDARY AND TOPOGRAPHIC SURVEY. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION MAY |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |