Notes
Date Text
2017-12-13 12:39:21THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. DETENTION POND STORMWATER TRACT 1 EXTENDS INTO
 PARCEL NO. 4 AND PARCEL NO. 5. IT'S BELIEVED THAT THIS
 PORTION OF THE DETENTION POND CONVEYS WATER TO THE
 CONTROL STRUCTURE FOR THE STORMWATER MANAGEMENT SYSTEM
 WILL A DRAINAGE EASEMENT BE CREATED OVER THIS PORTION
 OF THE DETENTION POND?
  
 2. WILL DRAINAGE EASEMENTS BE CREATED OVER THE
 STORMWATER SYSTEM? SEVERAL STORM PIPES CROSS PARCEL
 LINES.
  
 3. NO ENGINEERING PLANS WERE PROVIDED.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120