| Date |
Text |
| 2017-11-03 15:51:35 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. REVIEW LOCATIONS OF PROPOSED TREES AND UNDERGROUND |
| | UTILITIES. ROOT BARRIERS ADJACENT TO THE UTILITIES MAY |
| | BE NECESSARY. |
| | |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. PROVIDE A COPY OF THE MODIFICATION TO THE SFWMD ERP |
| | PERMIT AND SIGNED AND SEALED DRAINAGE CALCULATIONS. |
| | |
| | 3. PROVIDE A COPY OF THE MODIFICATION TO THE NPBCID |
| | PERMIT. |
| | |
| | 4. CONSIDER CONNECTING THE DRAINAGE PIPE PROPOSED IN |
| | THE AREA EAST OF RIGHT FIELD TO THE PROPOSED DRAINAGE |
| | STRUCTURE IN THE EXPANDED DETENTION AREA INSTEAD OF TO |
| | THE EXISTING INLET SOUTH OF THE DETENTION AREA TO AVOID |
| | HAVING TO MODIFY THE EXISTING INLET TO ACCEPT THE PIPE. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |