| 2017-09-07 13:26:33 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. LABEL VERTICAL DATUM ON THE ENGINEERING PLANS AND |
| | PROVIDE A CONVERSION EQUATION TO NGVD1929. |
| | |
| | 2. WILL THE SPEED BUMPS BE REPLACED IN THE NEW PARKING |
| | LOT? |
| | |
| | 3. UPDATE CITY DETAILS. |
| | |
| | 4. WHAT IS THE SCHEDULE FOR THE FUTURE PARKING LOT? |
| | WILL THE PROPOSED TREES ON THE SIDES OF THE CATCH BASIN |
| | IN THE PARKING LOT INTERFERE WITH THE DRAINAGE TO THE |
| | CATCH BASIN IN THE FUTURE? |
| | |
| | 5. CHECK THE EXFILTRATION CALCULATIONS ON SHEET PE-2.2. |
| | LENGTH OF TRENCH PROVIDED (605 LF) IS LESS THAN THE |
| | LENGTH OF TRENCH ALLOWED (REQUIRED?) (752 LF). SHEET |
| | PE-1.2 CALLS OUT 752 LF OF EXFILTRATION TRENCH. |
| | |
| | 6. STOP BAR AND STOP SIGN MAY BE NEEDED AT INTERSECTION |
| | OF LONG DRIVE LANE AND CENTER DRIVE AISLE. |
| | |
| | 7. CROSS WALK IS SHOWN TO HAVE 4? STRIPES INSTEAD OF |
| | 12?/24? AS DEPICTED IN FDOT STANDARD INDEX 17346 OR 12" |
| | ON PBC?S T-P-13. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROPOSED |
| | DEVELOPMENT. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |