Plan Review Notes
Plan Review Notes For Project Z17080018
Project Number Z17080018
Review Stop ENG - PPRC
Sequence Number 3
Notes
Date Text
2017-10-27 11:32:46CITY OF WEST PALM BEACH
 ENGINEERING SERVICES DEPARTMENT
 DATE: 10/27/2017
 PROJECT: GEORGIAN GARDENS APARTMENT
 ADDRESS: 4330 COMMUNITY DRIVE
 STATUS: PASSED WITH CONDITIONS
  
 IN THE NEXT PHASE, THE FOLLOWING GENERAL COMMENTS MUST
 BE ADDRESSED PRIOR TO ISSUANCE OF CONSTRUCTION
 AUTHORIZATION INCLUDING BUILDING PERMITS AND
 ENGINEERING DEVELOPMENT APPROVAL:
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK:
 HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR
 MS,-PERMITS-APPLICATIONS
  
 2. PLEASE SUBMIT THE LATEST VERSION OF THE 'AUTO-CALC
 CERTIFIED COST ESTIMATE FORM' FOR SUBMISSION TO CITY OF
 WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL
 WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE
 FOLLOWING LINK: HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-
 PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 3. PLACEMENT OF ANY PROPOSED METER, BACKFLOW PREVENTER,
 DCDA, CITY'S POINT OF SERVICE, ETC. SHALL BE INSTALLED
 PER THE CITY'S STANDARD DETAILS. WATER METER SHOULD BE
 WITHIN THE RIGHT-OF-WAY OR INSIDE AN 'UTILITY EASEMENT'
 JUST INSIDE THE PROPERTY NEAR THE RIGHT-OF-WAY AND
 ACCESSIBLE;
  
 4. RELOCATE THE WEST FIRE HYDRANT AND FIRE LINE WITHIN
 ADJACENT PROPERTY LIMITS;
  
 5. SUBMIT WITH THE ENGINEERING DEVELOPMENT APPROVAL
 APPLICATION SIGNED & SEALED ENGINEER/MEP WATER AND
 SANITARY SEWER CALCULATION (IN DETAIL I.E. AVERAGE AND
 PEAK WITH PEAKING FACTOR). SUBMIT CALCULATIONS TO
 VALIDATE METER SIZE SELECTION. SHOW THESE CALCULATIONS
 ON THE UTILITY PLAN SHEET AS WELL;
  
 6. SHOW ON THE FINAL PLANS WHERE ARE THE PROPOSED WATER
 AND SANITARY SEWER LINES ARE CONNECTED TO EXISTING
 WATER AND SEWER MAINS;
  
 7. PLEASE INCLUDE THE LATEST VERSION OF THE APPLICABLE
 CITY OF WEST PALM BEACH STANDARD UTILITY DETAILS TO THE
 DETAIL SHEET/S DURING SUBMISSION OF THE FINAL
 ENGINEERING PLANS. CONTACT THE ENGINEERING SERVICES
 DEPARTMENT FOR THE LATEST REVISED DETAILS IN CAD
 FORMAT. CITY'S STANDARD DETAILS (IN PDF FILE FORMAT)
 CAN BE DOWNLOADED FROM THE FOLLOWING SITE: HTTP://WPB.O
 RG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PERMITS-
 APPLICATIONS
  
 8. IN THE FINAL PLANS, MUST PROVIDE UTILITY CONFLICT
 TABLE (BOTTOM AND TOP OF CROSSING PIPES) AT THE
 CONFLICT POINTS OF ALL WATER, STORM AND SANITARY SEWER
 PIPES AS WELL AS OTHER FRANCHISE UTILITIES. EXISTING
 UTILITIES WITHIN THE PROPOSED SANITARY SEWER LATERAL
 ARE TO BE VERIFIED VIA SOFTDIGS, PROVIDE ALL UTILITY
 CROSSING INFORMATION;
  
 9. IN THE FINAL PLANS, SHOW DIRECTION OF FLOW FOR THE
 EXISTING SANITARY SEWER;
  
 10. PAVEMENT RESTORATION FOR OPEN CUT/TRENCH FOR
 UTILITY CONNECTION WORKS WILL NEED TO BE IN ACCORDANCE
 WITH 2016 CITY STANDARD DETAIL GC-9. THE ROAD SHALL BE
 MILLED/RESURFACED FOR FULL LANE WIDTH OF THE TRAVEL
 LANE(S) ENCROACHED BY THE TRENCH AREA, INCLUDING A
 TRANSITION AREA OF 50 FEET ON EACH SIDE OF THE TRENCH.
 PLEASE SHOW ON THE FINAL PLANS THE EXTENT OF THE
 MILLING AND RESURFACING;
  
 11. SHOW ON THE FINAL PLANS SIZE AND MATERIAL OF ALL
 EXISTING UTILITIES ON COMMUNITY DRIVE INCLUDING BUT NOT
 LIMITED TO WATER, SEWER, GAS, UNDERGROUND ELECTRIC
 CONDUITS ETC. PLEASE IDENTIFY THE SOURCE OF THE
 AS-BUILT INFORMATION UTILIZED FOR THE POTABLE WATER,
 SANITARY SEWER, AND STORM SEWER DESIGN;
  
 12. FOR THE FINAL WATER AND SEWER PLANS, INCLUDE A NOTE
 THAT: AS OF DECEMBER 20, 2015 THE CITY OF WEST PALM
 BEACH CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 MAKING KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD
 FREE." FOR MORE INFORMATION REFER TO THE LINK BELOW: HT
 TP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLICA
 TIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  
 13. ALL PROPOSED FIRE DEPARTMENT CONNECTIONS SHALL BE
 WITHIN 100 FEET OF A FIRE HYDRANT AND SHALL BE WITHIN
 AN EASEMENT WITHIN THE PROPERTY;
  
 14. SUBMIT ESTIMATES FOR WATER AND FIRE DEMAND, BOTH
 AVERAGE AND PEAK FLOW WITH PEAKING FACTOR. ALSO SUBMIT
 ESTIMATES OF SANITARY SEWER FLOW FOR THE PROPOSED
 DEVELOPMENT. SHOW PROJECTED DEMANDS ON THE UTILITY PLAN
 SHEET;
  
 15. THE AVAILABLE WATER PRESSURE IN THIS PORTION OF THE
 CITY MAY NOT BE ACCEPTABLE AT ELEVATIONS HIGHER THAN
 THE 2ND FLOOR. WE RECOMMEND A LONG-TERM PRESSURE STUDY
 BE PERFORMED PRIOR TO FINALIZATION OF THE UTILITY
 DESIGN;
  
 16. ON THE LANDSCAPING PLAN, ROOT BARRIERS MAY BE
 REQUIRED WHERE PLANTINGS ARE NEAR UNDERGROUND
 STORMWATER, SANITARY, OR POTABLE WATER LINES;
  
 SOFIA QUINONES-BENEJAM, EI
 PROJECT ENGINEER
 CITY OF WEST PALM BEACH
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33402
 (MAILING ADDRESS: PO BOX 3366)
 P: 561.494.1108
 C: 561.459.6518
 F: 561.494.1116
 EMAIL: [email protected]
  
  