| 2017-09-06 16:10:10 | PROJECT: PALM BEACH GARAGE Z17070013 |
| | SEPTEMBER 6, 2017 |
| | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND |
| | PROVIDE THE FOLLOWING COMMENTS: |
| | |
| | 1. THE APPROVED LANDSCAPE PLAN SHOWS THE PREVIOUSLY |
| | APPROVED TREES AND PALMS ON SITE. PLEASE ACCOUNT FOR |
| | ALL EXISTING TREES AND PALMS THAT MATCH THE APPROVED |
| | PLAN, AND LABEL THEM ON THE PROPOSED LANDSCAPE PLAN BY |
| | SPECIES. |
| | |
| | 2. PLEASE PROVIDE A TREE DISPOSITION LIST SHOWING TREES |
| | AND PALMS TO REMAIN, BE RELOCATED OR REMOVED. |
| | |
| | 3. PLEASE UPDATE THE OVERALL LANDSCAPE REQUIREMENT |
| | CHART TO CURRENT CODE REQUIREMENTS FOR SHADE TREES AND |
| | FLOWERING TREES FOR THE SITE. |
| | |
| | 4. THE LANDSCAPE BUFFER TREE REQUIREMENT CALCULATIONS |
| | ARE NOT MET ON THE PLAN FOR THE EAST BUFFER. PALMS MAY |
| | ONLY BE SUBSTITUTED AT A 3 TO 1 RATIO FOR REQUIRED |
| | TREES. |
| | |
| | 5. PLEASE PROVIDE AN UPDATED CHART SHOWING COMPLIANCE |
| | WITH FLORIDA FRIENDLY LANDSCAPING PER SECTION 94-442 |
| | (G). THIS INCLUDES SHOWING DROUGHT TOLERANCE LEVEL AND |
| | NATIVE SPECIES ON THE PLANT LIST AND PROVIDING THE |
| | REQUIRED 40 POINTS. |
| | |
| | 6. PLEASE SHOW LOCATIONS OF ROOT BARRIERS TO PROTECT |
| | INFRASTRUCTURE AND TREES FROM CONFLICTS. THIS INCLUDES |
| | WATER, SEWER, DRAINAGE, SIDEWALKS AND CURBS, AND ANY |
| | FIELD STRUCTURES THAT COULD BE IMPACTED BY TREE ROOTS. |
| | |
| | 7. PLEASE PROVIDE SCREENING FOR ALL GROUND MOUNTED |
| | EQUIPMENT AND UTILITIES. WATER BACKFLOW VALVES AND FPL |
| | TRANSFORMERS MUST HAVE SCREENING HEDGES. |
| | |
| | 8. TREE HEIGHTS NEED TO MEET THE REQUIRED 12 FEET |
| | HEIGHT SPECIFIED IN SECTION 94-445(4). |
| | |
| | 9. PARKING LOT LANDSCAPE AREAS MUST MEET THE |
| | REQUIREMENTS OF SECTION 94-443(C)(3) AND (4). PLEASE |
| | SHOW ALL CALCULATIONS AND PROVIDE A DIAGRAM SHOWING THE |
| | AREAS COUNTED TOWARD THIS REQUIREMENT. |
| | |
| | 10. PLEASE PROVIDE THE LOCATIONS OF LIGHTING ON THE |
| | LANDSCAPE PLAN. |
| | |
| | 11. PLEASE PROVIDE CALCULATIONS FOR THE REQUIRED |
| | BUILDING PERIMETER PLANTING OF 30 PERCENT FOR THE |
| | EXISTING BUILDING AND PROPOSED BUILDING PER SECTION |
| | 94-444(E)(1). |
| | |
| | 12. PALM IN THE TERMINAL LANDSCAPE ISLAND AT THE |
| | NORTHEAST CORNER OF THE PROPERTY DOES NOT MEET THE |
| | SHADE TREE REQUIREMENT OR THE BUFFER TREE REQUIREMENT. |
| | |
| | |
| | CONDITIONS OF APPROVAL |
| | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON |
| | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE |
| | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT |
| | SERVICES DEPARTMENT, PLANNING DIVISION. |
| | |
| |