2017-10-26 14:27:58CITY OF WEST PALM BEACH
 ENGINEERING SERVICES DEPARTMENT
 PROJECT NAME: TUXEDO AVENUE WAREHOUSE ? 1510 TUXEDO
 AVE. - Z17060018
 STATUS: FAILED
  
 THIS IS AN INITIAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS, AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES.
 THE FOLLOWING GENERAL COMMENTS MUST BE ADDRESSED PRIOR
 TO ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL:
  
 1. PROPOSED WATER AND SANITARY SEWER SERVICE MUST BE
 CONNECTED TO THE EXISTING WATER AND SEWER MAINS LOCATED
 ON THE PROPERTY FRONTAGE ROADS EITHER TUXEDO AVE. OR
 POINT RD.;
  
 2. REFER TO CITY?S STANDARD DETAIL GC-1 FOR CONCRETE
 SIDEWALK;
  
 3. REFER TO CITY?S STANDARD DETAIL GC-3 FOR CONCRETE
 CURB & GUTTER;
  
 4. REFER TO CITY?S STANDARD DETAIL GC-7 FOR CONCRETE
 DRIVEWAY APRONS;
  
 AFTER THE SITE PLAN IS APPROVED, IN THE NEXT PHASE, THE
 FOLLOWING GENERAL COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL:
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK: HTTP
 ://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-
 PERMITS-APPLICATIONS
  
 2. PLEASE SUBMIT THE LATEST VERSION OF THE ?AUTO-CALC
 CERTIFIED COST ESTIMATE FORM? FOR SUBMISSION TO CITY OF
 WEST PALM BEACH PUBLIC WORKS DEPARTMENT FOR ADDITIONAL
 WORK PROPOSED. THIS FORM CAN BE DOWNLOADED FROM THE
 FOLLOWING LINK: HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-
 PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 3. WHAT IS THE PLAN FOR FIRE PROTECTION FOR THE
 PROPOSED BUILDING? SHOW PROPOSED FIRE LINE AND BACKFLOW
 PREVENTER, METER ASSEMBLY ETC. IN THE UTILITY PLAN
 DURING FINAL PLANS SUBMITTALS;
  
 4. SUBMIT WITH THE ENGINEERING DEVELOPMENT APPROVAL
 APPLICATION SIGNED & SEALED ENGINEER/MEP WATER AND
 SANITARY SEWER CALCULATION (IN DETAIL I.E. AVERAGE AND
 PEAK WITH PEAKING FACTOR). SUBMIT CALCULATIONS TO
 VALIDATE METER SIZE SELECTION. SHOW THESE CALCULATIONS
 ON THE UTILITY PLAN SHEET AS WELL;
  
 5. SHOW THE NEAREST FIRE HYDRANT TO THIS SITE ON THE
 FINAL UTILITY PLAN. FIRE HYDRANT FLOW TEST DATA FROM
 EXISTING FIRE HYDRANT WILL BE REQUIRED PART OF THE PLAN
 SUBMITTAL. SHOW HYDRANT FLOW TEST DATA RESULT ON THE
 PLANS;
  
 6. PLEASE INCLUDE THE LATEST VERSION OF THE APPLICABLE
 CITY OF WEST PALM BEACH STANDARD UTILITY DETAILS TO THE
 DETAIL SHEET/S DURING SUBMISSION OF THE FINAL
 ENGINEERING PLANS. CONTACT THE ENGINEERING SERVICES
 DEPARTMENT FOR THE LATEST REVISED DETAILS IN CAD
 FORMAT. CITY?S STANDARD DETAILS (IN PDF FILE FORMAT)
 CAN BE DOWNLOADED FROM THE FOLLOWING SITE: HTTP://WPB.O
 RG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PERMITS-
 APPLICATIONS
  
 7. PLACEMENT OF THE ANY PROPOSED METER, BACKFLOW
 PREVENTER, DCDA ETC. SHALL BE INSTALLED PER THE CITY?S
 STANDARD DETAILS. WATER METER SHOULD BE WITHIN THE
 RIGHT-OF-WAY OR INSIDE AN 'UTILITY EASEMENT' JUST
 INSIDE THE PROPERTY NEAR THE RIGHT-OF-WAY AND
 ACCESSIBLE;
  
 8. IN THE FINAL PLANS, MUST PROVIDE UTILITY CONFLICT
 TABLE (BOTTOM AND TOP OF CROSSING PIPES) AT THE
 CONFLICT POINTS OF ALL WATER, STORM AND SANITARY SEWER
 PIPES AS WELL AS OTHER FRANCHISE UTILITIES. EXISTING
 UTILITIES WITHIN THE PROPOSED SANITARY SEWER LATERAL
 ARE TO BE VERIFIED VIA SOFTDIGS, PROVIDE ALL UTILITY
 CROSSING INFORMATION;
  
 9. IN THE FINAL PLANS, SHOW DIRECTION OF FLOW FOR THE
 EXISTING SANITARY SEWER. SHOW INVERT AT CONNECTION
 POINTS AND INCLUDE A PROFILE FOR THE PROPOSED SERVICE
 LATERAL WITH GROUND ELEVATIONS ABOVE THE PIPE;
  
 10. FOR THE FINAL WATER AND SEWER PLANS, INCLUDE A NOTE
 THAT: AS OF DECEMBER 20, 2015 THE CITY OF WEST PALM
 BEACH CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED,
 MAKING KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD
 FREE." FOR MORE INFORMATION REFER TO THE LINK BELOW: HT
 TP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLICA
 TIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  
 SOFIA QUINONES-BENEJAM, EI
 PROJECT ENGINEER
 CITY OF WEST PALM BEACH
 401 CLEMATIS STREET, 4TH FLOOR
 WEST PALM BEACH, FL 33402
 (MAILING ADDRESS: PO BOX 3366)
 P: 561.494.1108
 C: 561.459.6518
 F: 561.494.1116
 EMAIL: [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved