| 2017-04-11 14:16:13 | CITY OF WEST PALM BEACH |
| | ENGINEERING SERVICES DEPARTMENT |
| | |
| | DATE: 04/11/2017; |
| | |
| | STATUS: PASSED FOR THIS REVIEW LEVEL; |
| | |
| | Z17030030: 2300 PRESIDENTIAL WAY - BANYAN CAY PD MAJOR |
| | (PB CASE NO. 1624P) |
| | |
| | THIS IS AN INITIAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS, AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESS UPON SUBMISSION OF DETAILED |
| | ENGINEERING PLANS. THE FOLLOWING ARE GENERAL COMMENTS |
| | AT THIS LEVEL: |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED FROM THE FOLLOWING WEBSITE LINK: |
| | |
| | HTTP://WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FOR |
| | MS,-PERMITS-APPLICATIONS |
| | |
| | 2. FOR SANITATION/GARBAGE COLLECTION CONTACT THE CITY'S |
| | PUBLIC WORKS DEPARTMENT. FINAL APPROVED SITE PLANS NEED |
| | TO SHOW PROPOSED SANITATION COLLECTION PLANS AND |
| | DETAILS; AND WILL NEED APPROVAL FROM PETER BIENIEK, |
| | PUBLIC WORKS DIRECTOR. PLEASE INCLUDE THE CITY OF WEST |
| | PALM BEACH STANDARD DETAIL FOR THE DUMPSTER ENCLOSURE |
| | ON THE PLANS. MINIMUM DIMENSIONAL (E.G. THE GATE WIDTH |
| | MUST BE A MINIMUM OF 12.5 FEET) REQUIREMENTS FOR THE |
| | ENCLOSURE ARE LISTED IN CODE OF ORDINANCES, SECTION |
| | 94-444(B) OF THE CODE OF ORDINANCES. CITY STANDARD |
| | DETAIL GC-8 MAY BE DOWNLOADED AT: |
| | |
| | HTTP://WPB.ORG/ENGINEERING/ENGINEERING-SERVICES/ENGINEE |
| | RING-STANDARDS/ |
| | |
| | 3. SUBMIT ESTIMATES FOR WATER AND FIRE DEMAND, BOTH |
| | AVERAGE AND PEAK FLOW WITH PEAKING FACTOR FOR 150-ROOM |
| | HOTEL, GOLF CLUBHOUSE AND OTHER FACILITIES. ALSO SUBMIT |
| | ESTIMATES OF SANITARY SEWER FLOW FOR THE PROPOSED |
| | DEVELOPMENTS; |
| | |
| | 4. THE AVAILABLE WATER PRESSURE IN THIS PORTION OF THE |
| | CITY MAY NOT BE ACCEPTABLE AT ELEVATIONS HIGHER THAN |
| | THE 2ND FLOOR. WE RECOMMEND A LONG-TERM PRESSURE STUDY |
| | BE PERFORMED PRIOR TO FINALIZATION OF THE UTILITY |
| | DESIGN; |
| | |
| | 5. PLEASE PROVIDE AN AUTOTURN ANALYSIS DEMONSTRATING |
| | THE SOLID WASTE COLLECTION VEHICLE CAN ACCESS AND |
| | MANEUVER WITHIN THE PROPOSED HOTEL AND OTHER MULTI-USE |
| | FACILITIES WITHIN THE DEVELOPMENT. |
| | |
| | 6. ALL PROPOSED FIRE DEPARTMENT CONNECTIONS SHALL BE |
| | WITHIN 150 FEET OF A FIRE HYDRANT AND SHALL BE WITHIN |
| | AN EASEMENT WITHIN THE PROPERTY. LANDSCAPE PLAN SHALL |
| | SHOW LOCATIONS OF ALL WATER METERS, VALVES, CLEAN-OUTS, |
| | LIGHT POLES, ETC. ROOT BARRIERS MAY BE REQUIRED WHERE |
| | PLANTINGS ARE NEAR UNDERGROUND STORMWATER, SANITARY, OR |
| | POTABLE WATER LINES. |
| | |
| | MOSTAQUE KHAN, P.E. |
| | LAND DEVELOPMENT ENGINEER |
| | [email protected] |
| | 561-494-1124 (OFFICE) |
| | |
| |