2020-11-12 16:38:10PASSED, UNDER THE FOLLOWING CONDITIONS OF APPROVAL:
 1. CONDUCT TRAFFIC SIGNAL WARRANT ANALYSES AT QUADRILLE
 BOULEVARD/4TH STREET EVERY YEAR FOR 2 YEARS WHEN THE
 FOLLOWING CONDITIONS ARE MET:
 O CO IS ISSUED FOR AT LEAST 50% OF THE PROPOSED
 RESIDENTIAL UNITS, HOTEL OR GENERAL OFFICE USES, AND
 THE WESTBOUND APPROACH AT QUADRILLE BOULEVARD/4TH
 STREET IS OPERATING AT LOS F DURING WEEKDAY AM OR PM
 PEAK HOUR WHEN ANALYZED USING THE LATEST HIGHWAY
 CAPACITY MANUAL METHODOLOGY.
 O CO IS ISSUED FOR AT LEAST 85% OF THE PROPOSED
 RESIDENTIAL UNITS, HOTEL OR GENERAL OFFICE USES, AND
 THE WESTBOUND APPROACH AT QUADRILLE BOULEVARD/4TH
 STREET IS OPERATING AT LOS F DURING WEEKDAY AM OR PM
 PEAK HOUR WHEN ANALYZED USING THE LATEST HIGHWAY
 CAPACITY MANUAL METHODOLOGY.
 O THE LAST CO IS ISSUED FOR THE PROPOSED DEVELOPMENT.
 2. THE TRAFFIC SIGNAL ANALYSES SHOULD INCLUDE, AT A
 MINIMUM, WARRANT 1 EIGHT-HOUR VEHICULAR VOLUME, WARRANT
 2 FOUR-HOUR VEHICULAR VOLUME, WARRANT 4 PEDESTRIAN
 VOLUME, AND WARRANT 7 CRASH EXPERIENCE DOCUMENTED IN
 THE MANUAL ON UNIFORM TRAFFIC CONTROL DEVICES (MUTCD).
 THE NECESSARY TRAFFIC AND SAFETY DATA SHOULD BE
 COLLECTED FOR THE ANALYSES.
 3. SHOULD THE REQUEST FOR TRAFFIC SIGNAL BE DENIED, THE
 DEVELOPMENT SHOULD IMPLEMENT ALTERNATIVE MEASURES TO
 MITIGATE TRAFFIC CONGESTION AT QUADRILLE BOULEVARD/4TH
 STREET, INCLUDING BUT NOT LIMITED TO ADDITIONAL TDM
 MEASURES, WAYFINDING SIGNS TO DIVERT TRIPS TO THE
 QUADRILLE BOULEVARD/3RD STREET INTERSECTIONS, ETC. IN
 ADDITION, THE DEVELOPMENT SHOULD, ON CITY?S REQUEST,
 CONDUCT AN ENGINEERING STUDY FOR A POTENTIAL ENHANCED
 PEDESTRIAN CROSSWALK CROSSING QUADRILLE BOULEVARD AT
 4TH STREET, AND PURSUE SUCH A CROSSWALK APPROVAL WITH
 FDOT, AND IF APPROVED, CONSTRUCT SUCH ENHANCED
 CROSSWALK AT THE DEVELOPER?S OWN EXPENSES.
 4. PROVIDE SURETY FOR THE CONSTRUCTION OF A TRAFFIC
 SIGNAL AT QUADRILLE BOULEVARD/4TH STREET UNTIL THE
 OBLIGATIONS RELATED TO TRAFFIC SIGNAL WARRANT ANALYSES
 OR SIGNAL CONSTRUCTION (#1, #2 AND #3 ABOVE) ARE FULLY
 MET.
 5. PROVIDE SIDEWALK EASEMENT FOR THE PORTION OF
 SIDEWALK OUTSIDE RIGHT-OF-WAY.
 6. PROVIDE THE CITY A COPY OF THE UPDATED PARKING
 MANAGEMENT PLAN ANNUALLY, STARTING AT ONE (1) YEAR
 AFTER CO IS ISSUED FOR AT LEAST 50% OF THE PROPOSED
 RESIDENTIAL UNITS, HOTEL OR GENERAL OFFICE USES, UNTIL
 TWO (2) YEARS AFTER THE LAST CO IS ISSUED. THE PARKING
 MANAGEMENT PLAN SHOULD DOCUMENT THE USAGE AND
 SPILLBACK, IF ANY, AT THE 4TH STREET VALET STATION, AND
 ANY MEASURE IMPLEMENTED TO ADDRESS THE SPILLBACK, IF
 ANY.
 7. PROVIDE THE FOLLOWING TDM MEASURES:
 O AT LEAST 2 PARKING SPACES FOR CAR-SHARING SERVICES
 O MICROMOBILITY FACILITIES ON-SITE
  
 VALERIO ORICCHIO
 CITY TRANSPORTATION ENGINEER