Plan Review Notes
Plan Review Notes For Project Z17020040
Project Number Z17020040
Review Stop STORM
Sequence Number 1
Notes
Date Text
2017-03-08 12:34:40THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE
 AVAILABLE AT
 HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX?.
 PLEASE REVIEW THE MAPS AND VERIFY THAT THE NEW MAPS
 WILL NOT IMPACT THE PROPOSED PROJECT.
  
 2. THE FREEBOARD REQUIREMENT FOR STRUCTURES IN A
 SPECIAL FLOOD HAZARD AREA IS ONE FOOT ABOVE BASE FLOOD
 ELEVATION.
  
 3. PROVIDE ENGINEERING PLANS FOR WORK WITH IN THE 4TH
 STREET RIGHT-OF-WAY.
  
 4. CONSIDER MOVING WEIRS TO DRAINAGE STRUCTURE S-201.
  
 5. MOVE ONSITE EXFILTRATION TRENCH ALONG N. DIXIE
 HIGHWAY FURTHER INTO THE SITE SO WHEN THE EXFILTRATION
 TRENCH IS REHABILITATED IN A FEW YEARS, THE
 CONSTRUCTION WILL NOT ENCROACH INTO DIXIE HIGHWAY
 RIGHT-OF-WAY.
  
 6. STORM MANHOLE S-106 APPEARS TO BE LOCATED IN THE
 RIGHT-OF-WAY OF QUADRILLE BLVD.
  
 7. QUADRILLE BLVD IS MAINTAINED BY FDOT. APPROVAL FROM
 FDOT WILL BE NEEDED FOR WORK WITHIN THE RIGHT-OF-WAY.
  
 8. WHAT IS THE PHASING OF THE 4TH STREET UTILITY
 CONSTRUCTION AND ROAD DEMOLITION. THE WATER AND SEWER
 PLAN SHOWS A PROPOSED SEWER LATERAL RUNNING THROUGH AN
 EXISTING DRAINAGE INLET AT THE EAST END OF 4TH STREET.
  
 9. THE PROPOSED WEIR ELEVATION IS 11.00 FT NGVD. THE
 GRATE ELEVATION IS 12.25 FOR THE PROPOSED TRENCH DRAIN
 ACROSS THE DRIVEWAY ON N. DIXIE HIGHWAY. SUBMIT THE
 HYDRAULIC GRADE LINE FOR THE DRAINAGE SYSTEM FOR THE
 25-YEAR 3-DAY STORM DEMONSTRATING THE HGL IS BELOW THE
 TRENCH GRATE ELEVATION.
  
 10. DO NOT SHOW TYPE ?F? CURB AND GUTTER ON THE
 DRIVEWAY APRON TO DIXIE HIGHWAY.
  
 11. WOOD POWER POLE ENCROACHING ON DIXIE HWY DRIVEWAY
 APRON.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. PROVIDE ENGINEERING CALCULATIONS SIGNED AND SEALED
 BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER FOR THE
 MINIMUM REQUIRED STORM RUNOFF WATER QUALITY TREATMENT
 AND PEAK FLOOD STAGES FOR 5-YEAR 1-DAY, 25-YEAR 3-DAY
 AND 100-YEAR 3-DAY DESIGN STORMS PER SFWMD CRITERIA.
  
 3. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROPOSED
 DEVELOPMENT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved