| 2017-04-11 16:20:39 | CITY OF WEST PALM BEACH |
| | PUBLIC WORKS DEPARTMENT |
| | ENGINEERING DIVISION |
| | |
| | DATE: 04/11/2017 |
| | |
| | PROJECT NAME: 3200 PRESIDENTIAL WAY (BANYAN CAY GOLF |
| | COURSE MAINTENANCE FACILITY) |
| | |
| | Z17020023 |
| | |
| | 2ND/RE-SUBMITTAL REVIEW RESPONSE: PASSED WITH PROVISO |
| | |
| | AFTER REVIEWING THE REVISED PLANS, IT APPEARS THAT SOME |
| | OF THE COMMENTS HAVE BEEN ADDRESSED AND DEEM SATISFIED. |
| | WHEREAS, OTHER COMMENTS ARE ACKNOWLEDGED WITH A |
| | STATEMENT: "THIS WILL BE ADDRESSED AT THE TIME OF |
| | BUILDING PERMIT SUBMITTAL" IN THE WRITTEN LETTER OF |
| | RESPONSE TO THE PREVIOUS PPRC COMMENTS DATED MARCH 31, |
| | 2017. THE ACKNOWLEDGED COMMENTS ALONG WITH THE |
| | FOLLOWING ITEM ARE EXPECTED TO BE ADDRESSED DURING |
| | "ENGINEERING DEVELOPMENT APPLICATION" PHASE PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL: |
| | |
| | 7. IT IS PREFERRED THAT PROPOSED GOLF COURSE |
| | MAINTENANCE FACILITY HAVE SEPARATE SERVICE CONNECTIONS |
| | FOR DOMESTIC WATER LINE AND FIRE LINE. FOR THE DOMESTIC |
| | WATER SERVICE CITY'S POINT-OF-SERVICE WILL BEGIN AT THE |
| | WATER METER WHEREAS FOR FIRE LINE THE CITY'S |
| | POINT-OF-SERVICE SHALL BEGIN AT THE TAPPING |
| | SLEEVE/VALVE I.E. AT THE CONNECTION POINT TO THE |
| | EXISTING WATER MAIN ON PRESIDENTIAL WAY (PER NFPA 24); |
| | |
| | 10. COMMENT RELATED TO PLACEMENT OF WATER METER, |
| | BACKFLOW PREVENTER, DCDA ETC. NEED TO BE ADDRESSED |
| | DURING "ENGINEERING DEVELOPMENT APPLICATION" PHASE AND |
| | NOT "AT THE TIME OF CONSTRUCTION". HENCE DETAILS OF |
| | UTILITY CONNECTION INFORMATION NEED TO BE SHOWN ON THE |
| | FINAL ENGINEERING PLANS WHICH NEED TO BE APPROVED BY |
| | THE ENGINEERING SERVICES DEPARTMENT PRIOR TO |
| | CONSTRUCTION IS AUTHORIZED; |
| | |
| | 11. SHOW EXTENTS OF PAVEMENT RESTORATION ON THE FINAL |
| | WATER AND SEWER PLANS FOR UTILITY CONNECTION WORK |
| | WITHIN THE RIGHT-OF-WAY AND ALSO ATTACH THE LATEST |
| | CITY'S STANDARD DETAIL TO THE PLAN SET WHICH NEED TO BE |
| | APPROVED BY THE ENGINEERING SERVICES DEPARTMENT PRIOR |
| | TO CONSTRUCTION IS AUTHORIZED; |
| | |
| | MOSTAQUE KHAN, P.E. |
| | LAND DEVELOPMENT ENGINEER |
| | [email protected] |
| | 561-494-1124 (OFFICE) |
| | |
| |