| 2017-02-08 09:56:25 | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT |
| | APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT |
| | APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP:// |
| | WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER |
| | MITS-APPLICATIONS |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE |
| | PLAN APPROVAL: |
| | |
| | 1. CHECK SCALE BAR ON LANDSCAPE PLANS. |
| | |
| | 2. PROVIDE ROOT BARRIER DETAIL AND SHOW WHERE ROOT |
| | BARRIER IS TO BE INSTALLED ON THE LANDSCAPE PLANS. |
| | |
| | 3. CONGRESS AVE. IS MAINTAINED BY PALM BEACH COUNTY. |
| | COUNTY APPROVAL WILL BE REQUIRED FOR WORK WITHIN THE |
| | RIGHT-OF-WAY OF CONGRESS AVE. |
| | |
| | 4. SHOW UTILITIES ON THE GUARDHOUSE LANDSCAPE PLANS. |
| | |
| | 5. SHOW UTILITIES ON THE LANDSCAPE PLANS. |
| | |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT. |
| | THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS |
| | CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE |
| | ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS |
| | |
| | 2. PROVIDE ENGINEERING CALCULATIONS SIGNED AND SEALED |
| | BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER FOR THE |
| | MINIMUM REQUIRED STORM RUNOFF WATER QUALITY TREATMENT |
| | AND PEAK FLOOD STAGES FOR 5-YEAR 1-DAY, 25-YEAR 3-DAY |
| | AND 100-YEAR 3-DAY DESIGN STORMS PER SFWMD CRITERIA. |
| | |
| | 3. PROVIDE A COPY OF THE SFWMD ERP MODIFICATION FOR |
| | THIS PROPOSED DEVELOPMENT. |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| | [email protected] |
| | |
| |
Print |