| 2017-03-13 11:19:33 | CITY OF WEST PALM BEACH |
| | ENGINEERING SERVICES DEPARTMENT |
| | |
| | DATE: 03/13/2017 |
| | |
| | PROJECT NAME: PALM HARBOR MARINA HOTEL - Z16110016 - |
| | 300 N FLAGLER DRIVE |
| | |
| | 3RD REVIEW RESPONSE ON "CONCEPTUAL ENGINEERING PLANS": |
| | PASSED WITH PROVISO (SAME AND IN CONTINUATION OF THE |
| | 2ND REVIEW COMMENTS) |
| | |
| | 3RD SUBMITTAL OF THE CIVIL PLANS WAS RECEIVED AT THE |
| | DEV. SERVICES DEPT. ON 2/21/2017 WHICH HAS DID NOT HAVE |
| | PROPER REVISIONS FROM THE 2ND ROUND COMMENTS: |
| | |
| | ORIGINAL COMMENT FROM 2ND REVIEW: FOR PAVEMENT |
| | RESTORATION REFER TO CITY STANDARD DETAILS P-4 AND |
| | GC-9. EXTENTS OF PAVEMENT RESTORATION SHOWN ON THE |
| | PLANS (IN RESPONSE TO COMMENT NO. 18) ARE NOT ADEQUATE. |
| | |
| | NEW COMMENT: CONCEPTUAL ENGINEERING PLANS DO NOT SHOW |
| | PAVEMENT RESTORATION PROPERLY. LIMIT SHALL BE 50-FEET |
| | ON EACH SIDE OF THE PROPOSED UTILITY PIPES FROM THE |
| | EDGE OF THE TRENCH AS SHOWN ON CITY'S STD. DETAILS P-4 |
| | AND GC-9. PLEASE CORRECT THIS AND SHOW THE EXTENT ON |
| | THE FINAL ENGINEERING PLANS DURING 'ENGINEERING REVIEW |
| | APPLICATION' STAGE. FOR GARBAGE COLLECTION/SANITATION |
| | PLANS NOW NEED APPROVAL FROM PETER BIENIEK, PUBLIC |
| | WORKS DIRECTOR. |
| | |
| | TO RE-ITERATE THE MAIN PREVIOUS COMMENT/S : ALL |
| | PREVIOUSLY ACKNOWLEDGED RESPONSES AND ANY AND ALL |
| | COMMENTS THOSE HAVE NOT BEEN SATISFIED YET NEED TO BE |
| | ADDRESSED IN THE 'FINAL ENGINEERING PLANS' WHICH NEED |
| | TO BE SUBMITTED TO THE ENGINEERING DEPARTMENT ALONG |
| | WITH AN 'ENGINEERING DEVELOPMENT APPLICATION' PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | |
| | MOSTAQUE KHAN, P.E. |
| | LAND DEVELOPMENT ENGINEER |
| | [email protected] |
| | 561-494-1124 (OFFICE) |
| | |
| |