| 2017-04-03 16:35:11 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 |
| | PROJECT: 2001 S DIXIE Z16110015 |
| | APRIL 3, 2017 |
| | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND |
| | PROVIDE THE FOLLOWING COMMENTS: |
| | |
| | 1. NOT SATISFIED. PLEASE PROVIDE INFORMATION ON THE |
| | INSTALLATION AND COMPLETION OF THE APPROVED AND |
| | PERMITTED LANDSCAPING FOR THE CO OF THE EXISTING |
| | BUILDING, AND HOW THE TIMING OF THE CONSTRUCTION OF |
| | THIS ADDITION WOULD BE COORDINATED. |
| | |
| | THE CURRENT BUILDING IS OPERATING UNDER A TCO. IF THE |
| | LANDSCAPING IS COMPLETED TO PERMIT PLAN, AND |
| | CERTIFICATION FROM THE LANDSCAPE ARCHITECT CAN BE |
| | ISSUED, A FINAL INSPECTION SHOULD BE SCHEDULED AND THE |
| | LANDSCAPE PERMIT CLOSED OUT. |
| | |
| | 2. SATISFIED. PLEASE SHOW THE BUFFER PLANTINGS ALONG |
| | THE WEST PROPERTY LINE AS PREVIOUSLY APPROVED, AND |
| | LABEL ALL LANDSCAPE BUFFERS. |
| | |
| | 3. PARTIALLY SATISFIED. PLEASE CORRECT THE FOUNDATION |
| | PLANTING CALCULATION TO REFLECT THE PERCENTAGE OF THE |
| | ENTIRE BUILDING FOR REQUIRED AND PROVIDED LINEAR |
| | FOOTAGE TO MEET THE REQUIREMENTS OF SECTION |
| | 94-443(E)(1). |
| | THE PROPOSED BUILDING MEETS THE REQUIREMENT, BUT THE |
| | EXISTING BUILDING SHOWS ONLY 60 LINEAR FEET PROVIDED, |
| | NOT THE 100 INDICATED ON THE PLAN, AND SHORT OF THE 75 |
| | FEET REQUIRED. |
| | |
| | 4. NOT SATISFIED. PLEASE PROVIDE A STATUS UPDATE ON |
| | CONDITION #2 OF THE CURRENT APPROVAL REGARDING STREET |
| | TREES ON DIXIE. |
| | |
| | PER THE PLANNING AND ZONING ADMINISTRATOR, PLEASE |
| | PROVIDE ANY INFORMATION FROM FDOT TO SHOW THIS CANNOT |
| | BE ACCOMPLISHED. |
| | |
| | 5. SATISFIED. PLEASE PROVIDE LOCATIONS OF LIGHTING ON |
| | THE LANDSCAPE PLAN TO AVOID CONFLICTS WITH LANDSCAPING. |
| | |
| | MAY NEED TO BE ADJUSTED IF REQUIRED TREES FOR PARKING |
| | ARE ADDED IN THE NORTH DROP OFF AREA PARKING. |
| | |
| | 6. SATISFIED. PLEASE SHOW LOCATIONS OF ROOT BARRIERS TO |
| | PROTECT INFRASTRUCTURE AND TREES FROM CONFLICTS. THIS |
| | INCLUDES WATER, SEWER, DRAINAGE, SIDEWALKS AND CURBS, |
| | AND ANY FIELD STRUCTURES THAT COULD BE IMPACTED BY TREE |
| | ROOTS. |
| | |
| | 7. SATISFIED. PLEASE REMOVE THE REFERENCE TO THE OAK |
| | TREE IN THE RIGHT OF WAY AT THE SOUTH SIDE OF BISCAYNE |
| | DRIVE, AS IT HAS BEEN REMOVED. |
| | ADDITIONAL COMMENTS 4/3/17: |
| | 8. PLEASE PROVIDE THE REQUIRED TREE AND TERMINAL |
| | LANDSCAPE ISLAND ADJACENT TO EACH END OF THE ROW OF |
| | PARKING IN THE NORTH DROP OFF AREA. |
| | |
| | 9. PLEASE INDICATE CURBED BULB OUTS ADJACENT TO THE |
| | PARKING SPACES PROPOSED IN THE FLAMINGO DRIVE RIGHT OF |
| | WAY AND PROVIDE LANDSCAPING AND STREET TREES. |
| | |
| | 10. PLEASE INDICATE WHERE THE FPL TRANSFORMER IS |
| | PROPOSED IF IT IS NOT GOING TO REMAIN IN THE CURRENT |
| | LOCATION. |
| | PLEASE UNDERSTAND THAT ADDITIONAL INFORMATION MAY BE |
| | REQUESTED, AND STAFF MAY HAVE ADDITIONAL COMMENTS AS |
| | THE REVIEW PROCESS CONTINUES. |
| | |
| |