| Date |
Text |
| 2017-01-13 16:04:11 | FROM: RAY CARANCI, LANDSCAPE PLANNER 561-822-1462 |
| | PROJECT: HOME DEPOT CPD MAJOR Z16110014 |
| | JANUARY 13, 2017 |
| | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND |
| | PROVIDE THE FOLLOWING COMMENTS: |
| | |
| | |
| | 1. SATISFIED. PLEASE ADD THE REQUIRED TERMINAL |
| | LANDSCAPE ISLAND AND TREE AT THE END OF THE ROW OF |
| | PARKING ADJACENT TO THE SEATING AREA. |
| | |
| | 2. NOT SATISFIED. PLEASE SHOW LOCATIONS OF ROOT |
| | BARRIERS TO PROTECT INFRASTRUCTURE AND TREES FROM |
| | CONFLICTS. THIS INCLUDES WATER, SEWER, DRAINAGE, |
| | SIDEWALKS AND CURBS, AND ANY FIELD STRUCTURES THAT |
| | COULD BE IMPACTED BY TREE ROOTS. |
| | |
| | THREE MONTGOMERY PALMS ARE SHOWN DIRECTLY ON TOP OF |
| | WATER SERVICE ON THE FRONT OF THE BUILDING. ONE |
| | MONTGOMERY PALM BETWEEN THE PATIO AND LOADING ZONE IS |
| | SHOWN CLOSE TO THE SEWER LINE. PLEASE REVISE TO ADJUST |
| | LOCATIONS TO AVOID CONFLICTS AND ADD ROOT BARRIER WHERE |
| | NEEDED. |
| | |
| | 3. SATISFIED. THERE APPEARS TO BE A MISSING ROYAL PALM |
| | IN THE RIGHT OF WAY ADJACENT TO THE FRONT OF THE NEW |
| | BUILDING THAT MUST BE REPLACED. |
| | |
| | 4. NOT SATISFIED. ALL MISSING LANDSCAPING, PARTICULARLY |
| | REQUIRED TREES MUST BE REPLACED, AND ANY CHANGE IN |
| | SPECIES MAY BE ESTABLISHED AT THIS TIME. |
| | |
| | PLEASE REVISE THE PLAN SHEET MSP-3 TO SHOW REQUIRED |
| | TREES FOR THE LANDSCAPE ISLANDS IMMEDIATELY ADJACENT TO |
| | THE PROPOSED PARKING AREA. THE TREES SHOULD ALSO BE |
| | SHADOWED IN ON L1.00. |
| | |
| |