Plan Review Notes
Plan Review Notes For Project Z16080012
Project Number Z16080012
Review Stop ENG - PPRC
Sequence Number 3
Notes
Date Text
2017-03-28 15:54:27CITY OF WEST PALM BEACH
 ENGINEERING SERVICES DEPARTMENT
  
 PROJECT NAME: GREAT GULF - 1515 S. FLAGLER DR. -
 Z16080012 (CASE #: PB 1559J)
  
 RESUBMITTAL REVIEW RESPONSE/STATUS: PASSED WITH
 CONDITION
  
 DATE: MARCH 28, 2017
  
 AFTER A REVIEWING THE REVISED PLANS AND THE RESPONSE TO
 THE PREVIOUS PPRC COMMENTS (RECEIVED ON 3/22/2017), IT
 APPEARS THAT SOME OF THE COMMENTS HAVE BEEN SATISFIED
 AND SOME ARE ACKNOWLEDGED THE ACKNOWLEDGED COMMENTS AND
 A NEW COMMENT SHOWN BELOW ARE EXPECTED TO BE ADDRESSED
 DURING 'ENGINEERING DEVELOPMENT APPLICATION' PHASE
 PRIOR TO ISSUANCE OF CONSTRUCTION AUTHORIZATION
 INCLUDING BUILDING PERMITS AND ENGINEERING DEVELOPMENT
 APPROVAL:
  
 1. IN THE FINAL PLANS, SHOW CONFLICT INFORMATION
 (BOTTOM AND TOP OF CROSSING PIPES) AT THE CONFLICT
 POINTS OF THE PROPOSED WATER AND SANITARY SEWER PIPES
 WITH THE EXISTING AND PROPOSED STORM DRAINS JUST TO THE
 NORTH OF THE BUILDING AND INSIDE THE PROPERTY;
  
 2. IN THE REVISED PLANS PROPOSED MANHOLE THAT IS CALLED
 OUT AS CITY'S 'POINT-OF-SERVICE' IS SHOWN TO BE INSIDE
 THE PRIVATE PROPERTY. CITY'S 'POINT-OF-SERVICE' MANHOLE
 SHALL BE WITHIN THE CITY'S RIGHT-OF-WAY. PLEASE CORRECT
 IT IN THE FINAL PLANS;
  
 3. 'FIRE POINT-OF-SERVICE' SHALL BE, PER 2016 NFPA 24,
 FROM THE CONNECTION POINT OF THE PROPOSED FIRE LINE TO
 THE EXISTING WATER MAIN LOCATED WITHIN THE CITY'S
 RIGHT-OF-WAY I.E. WHERE TAPPING SLEEVE AND VALVES IS
 SHOWN TO BE FOR BOTH SOUTH FLAGLER DR. AND ARKONA CT.
 PLEASE REVISE AND SHOW ACCORDINGLY ON THE FINAL PLANS;
  
 4. AS OF DECEMBER 20, 2015 THE CITY OF WEST PALM BEACH
 CROSS-CONNECTION CONTROL MANUAL HAS BEEN REVISED MAKING
 KNOWN THAT "ALL BACKFLOW DEVICES MUST BE LEAD FREE." IN
 THE FINAL WATER AND SEWER PLANS, INCLUDE A NOTE STATING
 THAT. FOR MORE INFORMATION REFER TO THE LINK BELOW:
  
 HTTP://WPB.ORG/DEPARTMENTS/PUBLIC-UTILITIES/FORMS-PUBLI
 CATIONS/BACKFLOW-CROSS-CONNECTION-CONTROL-MANUAL
  
 5. RIGHT-OF-WAY PERMIT AND SUBMITTAL OF MAINTENANCE OF
 TRAFFIC (MOT) FOR WORK WITHIN THE CITY'S RIGHT-OF-WAY
 WILL BE REQUIRED PRIOR TO CONSTRUCTION BEGINS FOR THIS
 DEVELOPMENT.
  
 MOSTAQUE KHAN, P.E.
 LAND DEVELOPMENT ENGINEER