Plan Review Notes
Plan Review Notes For Project Z16080012
Project Number Z16080012
Review Stop STORM
Sequence Number 2
Notes
Date Text
2017-01-11 11:05:40THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE
 AVAILABLE AT
 HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX?.
 PLEASE REVIEW THE MAPS AND VERIFY THAT THE NEW MAPS
 WILL NOT IMPACT THE PROPOSED PROJECT.
  
 2. THE CITY COMMISSION RECENTLY PASSED A RESOLUTION
 INCREASING THE FREEBOARD REQUIREMENT TO ONE FOOT ABOVE
 BASE FLOOD ELEVATION FOR STRUCTURES IN A SPECIAL FLOOD
 HAZARD AREA.
  
 3. INDICATE ON THE PAVING, GRADING AND DRAINAGE PLANS
 THAT THE PIPE CONNECTIONS FOR BUILDING PLUMBING ARE FOR
 RAIN WATER LEADERS ONLY. INDICATE IF THESE BUILDING
 PLUMBING PIPES WILL BE USED FOR FLOW OTHER THAN STORM
 WATER RUNOFF.
  
 4. THE BUILDING INCLUDES A BASEMENT WITH A FINISHED
 FLOOR ELEVATION AT (-)1.0 FT NGVD. INDICATE HOW
 GROUNDWATER WILL BE CONTROLLED AND WHERE THE
 GROUNDWATER WILL BE DISCHARGED TO.
  
 5. THE ONSITE DRAINAGE SYSTEM SHOULD TAKE INTO ACCOUNT
 SEA LEVEL RISE.
  
 6. INCLUDE THE STORMWATER MANAGEMENT SYSTEM WITH THE
 OTHER UTILITIES ON THE LANDSCAPE PLANS.
  
 7. TRY TO AVOID PLACING MANHOLES WITHIN THE SIDEWALK.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. PROVIDE ENGINEERING CALCULATIONS SIGNED AND SEALED
 BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER FOR THE
 MINIMUM REQUIRED STORM RUNOFF WATER QUALITY TREATMENT
 AND PEAK FLOOD STAGES FOR 5-YEAR 1-DAY, 25-YEAR 3-DAY
 AND 100-YEAR 3-DAY DESIGN STORMS PER SFWMD CRITERIA.
  
 3. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROJECT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved