Notes
Date Text
2016-09-14 08:17:13THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. IS DETENTION POND IN SOUTHWEST AREA OF SITE
 HYDRAULICALLY CONNECTED TO EXISTING LAKE. IF SO, HOW
 WILL THE DETENTION AREA BE HYDRAULICALLY CONNECTED TO
 THE PROPOSED RETENTION LAKE?
  
 2. THE SURVEY SHOWS THE EXISTING LAKE WITH A WATER
 SURFACE ELEVATION OF 14.6 FEET NGVD. HOW WILL THE WATER
 LEVEL IN THE PROPOSED RETENTION LAKE BE CONTROLLED AT
 ELEVATION 14.0? IF THERE IS A CONTROL STRUCTURE WITH
 OFFSITE DISCHARGE THEN LABEL THE RETENTION LAKE AS A
 DETENTION LAKE AND SHOW THE LOCATION OF THE CONTROL
 STRUCTURE.
  
 3. PROVIDE EXISTING AND PROPOSED STAGE STORAGE
 RELATIONSHIPS FOR THE EXISTING AND PROPOSED LAKES.
  
 4. IS THE PROPOSED LAKE SIZED FOR THE FUTURE
 DEVELOPMENT?
  
 5. HOW DEEP WILL THE PROPOSED LAKE BE? WILL THE LAKE
 HAVE LITTORAL PLANTINGS FOR WATER QUALITY TREATMENT?
  
 6. LABEL THE VERTICAL DATUM ON THE CONCEPTUAL PAVING
 AND DRAINAGE PLAN.
  
 7. THE EXISTING LAKE TO RECEIVE CLEAN FILL.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. PROVIDE ENGINEERING CALCULATIONS SIGNED AND SEALED
 BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER
 INDICATING THE CHANGES TO THE ONSITE PEAK FLOOD STAGES
 WILL NOT EXCEED THE SFWMD PERMITTED FLOOD STAGES AND
 STORMWATER TREATMENT IS BEING PROVIDED PER SFWMD
 CRITERIA.
  
 3. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROJECT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  
  Print


Account Summary | Usage Policy | Privacy Policy
Copyright © 2005 – 2014, SunGard Pentamation, Inc & City of West Palm Beach, FL – All Rights Reserved