| Plan Review Notes For Project Z16080007 |
| Project Number |
Z16080007 |
|
| Review Stop |
STORM |
| Sequence Number |
3 |
|
| Notes |
| Date |
Text |
| 2016-11-18 10:34:21 | COMMENTS BELOW ARE FROM THE REVIEW OF THE 11/10/2016 | | | PLANS AND RESPONSE LETTER. | | | | | | 1. ADD VERTICAL DATUM REFERENCE ON WATER AND SEWER PLAN | | | SHEET WS-1. | | | | | | 2. SHEET NUMBER (D-3?) FOR THIRD DETAILS SHEET DID NOT | | | PLOT. | | | | | | 3. PLANS CONTAIN TWO DETAILS (SEE SHEET PDD-2 AND SHEET | | | D-4) FOR THE EXFILTRATION TRENCH. ONLY SHOW THE DETAIL | | | THAT THE CONTRACTOR SHOULD FOLLOW. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | [email protected] | | | 561-494-1120 |
| |
Print |
|