Plan Review Notes
Plan Review Notes For Project Z16070022
Project Number Z16070022
Review Stop STORM
Sequence Number 3
Notes
Date Text
2017-11-20 17:31:07COMMENTS BELOW ARE FROM THE REVIEW OF THE NOVEMBER 7,
 2017 PACKAGE FROM E. SCHNEIDER INCLUDING ENGINEERING
 PLANS SIGNED AND SEALED ON 11/3/2017 AND COMMENT
 RESPONSE LETTER DATED NOVEMBER 3, 2017.
  
 1. REVISE TYPICAL CROSS SECTIONS A-A AND B-B ON SHEET
 PDD-3 TO ILLUSTRATE SAPODILLA AVE IS A CROWNED ROADWAY
 AND NOT A SHED SECTION. REVISE PAVEMENT DESIGN OF LANE
 ADDITION TO MATCH CITY STANDARD DETAIL GC-5.
  
 2. ADD DRAINAGE STRUCTURES BEFORE (UPSTREAM OF) THE
 CROSS WALKS AT THE INTERSECTION OF IRIS AND SAPODILLA
 TO LIMIT THE AMOUNT OF STORMWATER RUNOFF FLOWING ACROSS
 THE CROSSWALKS (REPEAT COMMENT). THE RESPONSE DISCUSSED
 PLACEMENT OF A TRENCH DRAIN BEFORE THE CROSS WALKAT THE
 INTERSECTION OF SAPODILLA. THE COMMENT IS REFERRING TO
 THE CROSSWALKS ACROSS IRIS (SW CORNER TO NW CORNER) AND
 ACROSS SAPODILLA (SW CORNER TO EAST SIDE OF STREET) AT
 THE INTERSECTION OF IRIS ST. AND SAPODILLA AVE.
  
 3. IDENTIFY WHERE THE ONSITE DRAINAGE CONTROL
 STRUCTURES WLL BE. ONSITE DRAINAGE SYSTEMS SHOULD BE
 LOCATED UPSTREAM OF THE CONTOL STRUCTURES (REPEAT
 COMMENT). STRUCTURES EX-MH4 ON SHEET PD-1 AND EX-CS ON
 SHEET PD-2 WERE THE ONLY STRUCTURES IDENTIFIED WITH
 WEIRS TO HOLD BACK AND CONTROL THE DISCHARGE OF
 STORMWATER FROM THE ONSITE DRAINAGE SYSTEMS. PLEASE
 EXPLAIN THE PURPOSE OF THE WEIR IN STRUCTURE EX-MH4 IF
 IT CONTROLS THE FLOW FROM THE KRAVIS SITE. IT MAY NEED
 TO BE MOVED TO A STRUCTURE THAT IS WITHIN THE KRAVIS
 PROPERTY. EXPLAIN HOW THE EXFILTRATION SYSTEM BETWEEN
 STRUCTURES EX-S5S AND S-1 WILL BE SURCHARGED.
  
 4. THE PROPOSED PIPE BETWEEN S-4 AND EX-CS NEEDS TO
 ENTER STRUCTURE EX-CS UPSTREAM OF THE WEIR.
  
 5. SHEET DEM-1 NEEDS TO CALLOUT THE REMOVAL OF THE
 EXISTING CATCH BASIN INLET ON THE SOUTHWEST CORNER OF
 SAPODILLA AND IRIS.
  
 6. ON SHEET PD-2, THE PROPOSED GRADES FOR THE CROSSWALK
 ACROSS THE RAMP UP TO THE PUBLIC PARKING GARAGE
 INDICATE FLOW COMING DOWN THE RAMP WILL FLOW DOWN THE
 SIDEWALK LANDING AT THE WEST END OF THE CROSSWALK. IF
 THIS IS THE DESIGN INTENT, EROSION PROTECTION MAY BE
 NEEDED ALONG THE SIDE SLOPE.
  
 7. IS A HANDRAIL PROPOSED FOR THE SIDEWALK ALONG THE
 WEST SIDE OF THE EXITING DRIVEWAY TO OKEECHOBEE BLVD
 FROM THE PUBLIC PARKING GARAGE. THE LONGITUDINAL SLOPE
 APPEARS STEEPER THAN 5%.
  
 8. ON SHEET SMP-1, THE YIELD HERE TO PEDESTRIAN SIGN AT
 THE DRIVEWAY TO IRIS ST. FROM THE PROPOSED VALET
 PARKING GARAGE IS POSTED AFTER THE SIDEWALK.
  
 TRACY L WARD, P.E.
 ENGINEERING SERVICES DEPARTMENT
 [email protected]
 561-494-1120