| Plan Review Notes For Project Z16070018 |
| Project Number |
Z16070018 |
|
| Review Stop |
STORM |
| Sequence Number |
3 |
|
| Notes |
| Date |
Text |
| 2018-01-26 14:32:27 | THE FOLLOWING COMMENTS ARE FROM THE REVIEW OF THE | | | 12/19/17 REVIEW SUBMITTAL: | | | | | | 1. THE TREE ROOT DETAIL IN THE LANDSCAPE PLANS MAKE | | | REFERENCE TO PBCWUD UTILITIES. ADD A REFERENCE TO CWPB | | | UTILTIES (WATER, SEWER, STORM). [REPEAT COMMENT]. | | | | | | 2. SHOW ROOT BARRIER ON THE LANDSCAPE PLANS FOR THE | | | STORM PIPE BETWEEN THE EXISTING CB (BEING CONVERTED TO | | | MH COVER) AND STRUCTURE S-105. | | | | | | 3. THE ENGINEERING PLAN DOES NOT MATCH THE SITE PLAN | | | AND LANDSCAPE PLANS. THE ENGINEERING PLAN DOES NOT SHOW | | | THE LANDSCAPE ISLAND ON THE SOUTHWEST SIDE OF THE | | | HANDICAP PARKING SPACES. | | | | | | 4. DRAINAGE STRUCTURE S-101 IS TO HAVE TWO PRBS BECAUSE | | | IT IS CONNECTED TO TWO EXFILTRATION TRENCHES. VERIFY | | | THE PRBS WILL FIT IN A TYPE 'C' DITCH BOTTOM INLET. | | | | | | 5. VERIFY THE EXISTING CB NORTH OF STRUCTURE S-101 WILL | | | HAVE A TWO FOOT SUMP IN ORDER FOR A PRB TO BE INSTALLED | | | ON THE SOUTH WALL. | | | | | | 6. EXTEND THE SIDEWALK WITH CURB RAMPS TO THE EDGE OF | | | PAVEMENT ON EACH SIDE OF BOYD STREET. | | | | | | TRACY L. WARD, P.E. | | | SENIOR STORMWATER ENGINEER | | | ENGINEERING SERVICES DEPARTMENT | | | 561-494-1120 | | | [email protected] |
| |
Print |
|