| Plan Review Notes For Project Z16020016 |
| Project Number |
Z16020016 |
|
| Review Stop |
STORM |
| Sequence Number |
2 |
|
| Notes |
| Date |
Text |
| 2017-09-05 14:17:09 | COMMENTS BELOW ARE BASED ON THE AUGUST 15, 2017 REVIEW | | | PACKAGE: | | | | | | 1. NEW FEMA FIRM MAPS AND TWO FEET OF FREEBOARD ABOVE | | | BASE FLOOD ELEVATION FOR STRUCTURES IN SPECIAL FLOOD | | | HAZARD AREAS WILL BE EFFECTIVE ON OCTOBER 5, 2017 IF | | | RESOLUTION PASSES AT SECOND READING BEFORE CITY | | | COMMISSION. | | | | | | 2. LIMIT THE NUMBER OF CONNECTIONS BETWEEN THE PRIVATE | | | STORM DRAINAGE SYSTEM AND THE CITY'S MS4 SYSTEM TO NO | | | MORE THAN ONE (1). | | | | | | 3. PREDEVELOPMENT CONDITIONS SHOULD BE BASED ON CURRENT | | | STATE OF THE PROPERTY (E.G. NEARLY PERVIOUS / | | | UNDEVELOPED). | | | | | | 4. LABEL 4TH STREET AS PRIVATE RIGHT-OF-WAY. | | | | | | TRACY L. WARD, P.E. | | | ENGINEERING SERVICES DEPARTMENT | | | [email protected] | | | 561-494-1120 | | | |
| |
Print |
|