2016-03-08 15:04:10CITY OF WEST PALM BEACH
 PUBLIC WORKS DEPARTMENT
  
 THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL.
  
 1. PLEASE SUBMIT A COPY OF THE SURVEY.
  
 2. PLEASE REVISE THE COVER SHEET TO REFLECT THE CORRECT
 DEPARTMENT. (DEPARTMENT OF ENGINEERING SERVICES DOES
 NOT EXIST.)
  
 3. PLEASE SPECIFY THE VERTICAL DATUM ON THE CIVIL
 PLANS.
  
 4. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE
 AVAILABLE AT HTTP://WWW.CO.PALM-BEACH.FL.US/NEWSROOM/08
 14/08-26-14-FLOOD_MAPS.HTM. PLEASE REVIEW THE MAPS AND
 VERIFY THAT THE NEW MAPS WILL NOT IMPACT THE PROPOSED
 PROJECT.
  
 5. DETAILS SHEETS WILL NEED TO UTILIZE STANDARD CITY OF
 WEST PALM BEACH DETAILS, WHICH MAY BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 6. WHAT IS BEING DISCHARGED FROM THE SUMP DRAIN INTO
 THE DRAINAGE SYSTEM?
  
 7. PLEASE REVIEW THE PROPOSED CATCH BASIN INLET FOR
 CONSTRUCTABILITY AND SEPARATION REQUIREMENTS. THE
 PROPOSED CATCH BASIN INLET IS LESS THAN 3 FEET FROM 60?
 PIPE LINE AND LESS THAN 5 FEET FROM 30? RAW WATER LINE.
 PLEASE ALSO REVIEW THE LOCATION OF THE PROPOSED
 EXFILTRATION TRENCH, WHICH IS LESS THAN 5 FEET FROM 30?
 RAW WATER LINE.
  
 8. HOW MUCH COVER WILL REMAIN OVER THE EXISTING
 DRAINAGE SYSTEM IN THE DRY RETENTION POND?
  
 9. DRY RETENTION POND APPEARS TO HAVE 1:1 SIDE SLOPES.
 HOW WILL THIS BE MAINTAINED?
  
 10. PLEASE REVISE THE PLANS TO COMPLY WITH CODE SECTION
 94-485 FOR PARKING LOT STRIPING (DOUBLE LINES CONNECTED
 AT END).
  
 11. ARE PAVERS PROPOSED AS PART OF THE PROJECT?
 STRIPING DETAIL CALLS OUT MATERIAL FOR PAVER SYSTEMS.
  
 12. NO DIRECT STORMWATER RUNOFF FROM ROADWAY AND
 PARKING LOTS SHOULD ENTER INTO EAST LAKE. RUNOFF SHOULD
 BE COLLECTED IN INLETS, SWALES OR DRY RETENTION AREAS.
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING DIVISION OF THE PUBLIC
 WORKS DEPARTMENT. THE ENGINEERING DEVELOPMENT APPROVAL
 APPLICATION FORMS CAN BE DOWNLOADED AT
 HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/
  
 2. PLEASE PROVIDE A COPY OF THE MODIFICATION OF SFWMD
 PERMIT.
  
  
 KELLY CRANFORD, P.E.
 CAPITAL IMPROVEMENT PLAN MANAGER
 [email protected]
 561-494-1098 (OFFICE)
  
 VINCE NOEL, PSM
 CITY SURVEYOR / REAL ESTATE SUPERVISOR
 [email protected]
 561-494-1096
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 561-494-1120
 [email protected]
  
  