Plan Review Notes
Plan Review Notes For Project Z16020011
Project Number Z16020011
Review Stop STORM
Sequence Number 2
Notes
Date Text
2016-10-12 15:07:47THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL
 DETAILS, DESIGN CALCULATIONS AND THE POLLUTION
 PREVENTION PLAN WILL BE REVIEWED AS PART OF THE
 ENGINEERING DEVELOPMENT APPROVAL AND BUILDING PERMIT
 APPLICATION PROCESSES. THE ENGINEERING DEVELOPMENT
 APPROVAL APPLICATION FORMS CAN BE DOWNLOADED AT HTTP://
 WPB.ORG/DEPARTMENTS/ENGINEERING-PUBLIC-WORKS/FORMS,-PER
 MITS-APPLICATIONS
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO SITE
 PLAN APPROVAL:
  
 1. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE
 AVAILABLE AT
 HTTP://MAPS.CO.PALM-BEACH.FL.US/GIS/FLOODZONES.ASPX?.
 PLEASE REVIEW THE MAPS AND VERIFY THAT THE NEW MAPS
 WILL NOT IMPACT THE PROPOSED PROJECT.
  
 2. THE CITY COMMISSION RECENTLY PASSED A RESOLUTION
 INCREASING THE FREEBOARD REQUIREMENT TO ONE FOOT ABOVE
 BASE FLOOD ELEVATION FOR STRUCTURES IN A SPECIAL FLOOD
 HAZARD AREA.
  
 3. MOVE HIGH POINT FOR WEST DRIVEWAY FURTHER WEST TO
 REDUCE THE AMOUNT OF RUNOFF FLOWING TO THE
 RIGHT-OF-WAY.
  
 4. THE ?CORE EX. CATCH BASIN? NOTE ON PLAN REFERENCES
 HDPE PIPE. IT SHOULD REFERENCE RCP PIPE.
  
 5. PROVIDE INVERT ELEVATION FOR 15? RCP PIPE AT
 EXISTING STRUCTURE.
  
 6. IS NOTE 3 ON SHEET C-1 (?? ASSUMED HYDRAULIC
 CONDUCTIVITY ??) STILL VALID?
  
 7. MODIFY/REPLACE EXISTING INLET TO VALLEY GUTTER TOP.
  
 8. UPDATE CITY DETAILS
  
 THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO
 ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING
 BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL.
  
 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL
 BE REQUIRED FROM THE ENGINEERING SERVICES DEPARTMENT.
 THE ENGINEERING DEVELOPMENT APPROVAL APPLICATION FORMS
 CAN BE DOWNLOADED AT: HTTP://WPB.ORG/DEPARTMENTS/ENGINE
 ERING-PUBLIC-WORKS/FORMS,-PERMITS-APPLICATIONS
  
 2. PROVIDE ENGINEERING CALCULATIONS SIGNED AND SEALED
 BY A FLORIDA REGISTERED PROFESSIONAL ENGINEER
 INDICATING THE CHANGES TO THE ONSITE PEAK FLOOD STAGES
 WILL NOT EXCEED THE SFWMD PERMITTED FLOOD STAGES AND
 STORMWATER PRE-TREATMENT VOLUMES ARE BEING PROVIDED PER
 SFWMD CRITERIA.
  
 3. PROVIDE A COPY OF THE SFWMD ERP FOR THIS PROPOSED
 DEVELOPMENT.
  
 TRACY WARD, PE
 SENIOR STORMWATER ENGINEER
 ENGINEERING SERVICES DEPARTMENT
 561-494-1120
 [email protected]
  