| 2016-01-12 08:20:48 | CITY OF WEST PALM BEACH |
| | PUBLIC WORKS DEPARTMENT |
| | THIS IS A CONCEPTUAL LEVEL REVIEW. CONSTRUCTION LEVEL |
| | DETAILS, DESIGN CALCULATIONS AND THE POLLUTION |
| | PREVENTION PLAN WILL BE REVIEWED AS PART OF THE |
| | BUILDING PERMIT APPLICATION PROCESSES. |
| | 1. WILL THE WASH WATER BE RECYCLED? THE WATER CANNOT BE |
| | DIRECTED TO THE SANITY SYSTEM WITHOUT THE INSTALLATION |
| | OF AN INTERCEPTOR (ORDINANCE 90-125). WASH WATER MAY |
| | NOT BE DIRECTED TO THE STORMWATER SYSTEM. PREFERABLY, |
| | THE WASH WATER SHOULD BE COLLECTED IN A WASH PIT AND |
| | DISPOSED OF BY AN INDUSTRIAL WASTE COMPANY. |
| | 2. PRELIMINARY, UPDATED FEMA FLOOD INSURANCE MAPS ARE |
| | AVAILABLE AT HTTP://WWW.CO.PALM-BEACH.FL.US/NEWSROOM/08 |
| | 14/08-26-14-FLOOD_MAPS.HTM. PLEASE REVIEW THE MAPS AND |
| | VERIFY THAT THE NEW MAPS WILL NOT IMPACT THE PROPOSED |
| | PROJECT. |
| | 3. PLEASE PROVIDE AN AUTOTURN ANALYSIS DEMONSTRATING |
| | THE SOLID WASTE COLLECTION VEHICLE CAN ACCESS THE |
| | PROPOSED DUMPSTER AND COMPACTOR LOCATIONS. THE TRASH |
| | DUMPSTER/COMPACTORS MUST LOCATED IN AREAS EASILY |
| | SERVICED BY THE CITY SANITATION EQUIPMENT AND MANPOWER |
| | PER SECTION 74-35(A)(5) OF THE CODE OF ORDINANCES. IF A |
| | ROLL-OFF COMPACTOR IS PROPOSED, PLEASE PROVIDE A LETTER |
| | FROM THE PRIVATE PROVIDER VERIFYING THAT THEY CAN |
| | PROVIDE SERVICE WITH THE CONFIGURATION SHOWN ON THE |
| | PLANS. |
| | 4. PLEASE REVISE THE LANDSCAPE PLAN TO SHOW LOCATIONS |
| | OF ALL WATER METERS, VALVES, CLEAN-OUTS, LIGHT POLES, |
| | ETC. ROOT BARRIERS MAY BE REQUIRED WHERE PLANTINGS ARE |
| | NEAR UNDERGROUND STORMWATER, SANITARY, OR POTABLE WATER |
| | LINES. |
| | 5. REMOVE THE PARKING SPACE AT THE CAR WASH EXIT. |
| | 6. SUBMIT UPDATED STORMWATER MANAGEMENT CALCULATIONS |
| | INDICATING THE PROJECTS MEETS THE C-51 DRAINAGE BASIN |
| | REQUIREMENTS. DRAINAGE DESIGN CALCULATIONS MUST |
| | DEMONSTRATE WATER QUALITY TREATMENT AND STORM |
| | ATTENUATION ARE PROVIDED ON-SITE. (ORDINANCE 4303-10) |
| | THE FOLLOWING COMMENTS MUST BE ADDRESSED PRIOR TO |
| | ISSUANCE OF CONSTRUCTION AUTHORIZATION INCLUDING |
| | BUILDING PERMITS AND ENGINEERING DEVELOPMENT APPROVAL. |
| | 1. AN ENGINEERING DEVELOPMENT APPROVAL APPLICATION WILL |
| | BE REQUIRED FROM THE ENGINEERING DIVISION OF THE PUBLIC |
| | WORKS DEPARTMENT. THE ENGINEERING DEVELOPMENT APPROVAL |
| | APPLICATION FORMS CAN BE DOWNLOADED AT |
| | HTTP://WPB.ORG/ENGINEERING/FORMS-AND-PUBLICATIONS/ |
| | |
| | |
| | KELLY CRANFORD, P.E. |
| | PUBLIC WORKS CIP MANAGER |
| | [email protected] |
| | 561-494-1098 (OFFICE) |
| | |
| | VINCE NOEL, PSM |
| | CITY SURVEYOR / REAL ESTATE SUPERVISOR |
| | [email protected] |
| | 561-494-1096 |
| | |
| | BRIAN COLLINS, PE |
| | CITY TRAFFIC ENGINEER |
| | [email protected] |
| | 561-494-1040 |
| | |
| | FERDINAND RIVERA |
| | PUBLIC WORKS OPERATIONS MANAGER |
| | [email protected] |
| | 561-822-2076 |
| | |
| | TRACY WARD, PE |
| | SENIOR STORMWATER ENGINEER |
| | 561-494-1120 |
| | [email protected] |
| | |
| |