| Date |
Text |
| 2015-11-24 16:27:16 | FROM: RAY CARANCI, LANDSCAPE PLANNER |
| | PROJECT: BROWN DISTRIBUTION RESUBMITTAL |
| | NOVEMBER 24, 2015 |
| | |
| | I HAVE REVIEWED THE ABOVE REFERENCED PETITION, AND |
| | PROVIDE THE FOLLOWING COMMENTS: |
| | |
| | 1. SATISFIED. PLEASE PROVIDE A TREE SURVEY IDENTIFYING |
| | EXISTING TREES ON THE PROPERTY AND INDICATE THE |
| | SPECIES, SIZE, AND IF THEY WILL BE REMOVED, RELOCATED, |
| | OR REMAIN. PLEASE REVISE HE MITIGATION CHART TO REFLECT |
| | THE TREE INVENTORY, AND PROVIDE PERTINENT INFORMATION |
| | FOR EACH TREE PER SECTION 94-448 (E) INCLUDING SPECIES, |
| | CANOPY SIZE AND REPLACEMENT REQUIREMENT FOR ANY TREES |
| | PROPOSED TO BE REMOVED. |
| | |
| | 2. SATISFIED. PLEASE PROVIDE THE DROUGHT TOLERANCE |
| | LEVEL FOR EACH PLANT SPECIES ON THE PLANT LIST, TO SHOW |
| | COMPLIANCE WITH SECTION 94-442(G) FLORIDA FRIENDLY |
| | LANDSCAPING REQUIREMENTS. PLEASE LABEL THE SECTION IN |
| | THE CHART AS SUCH. ADDING A COLUMN IDENTIFYING NATIVE |
| | PLANTS IS ALSO SUGGESTED. |
| | |
| | 3. SATISFIED. NUMBER OF FLOWERING TREES DOES NOT MEET |
| | THE REQUIRED NUMBER. |
| | |
| | 4. SATISFIED. PLEASE CHECK ALL CALCULATIONS FOR BUFFER |
| | AND REQUIRED TREES TO INCLUDE ADDITIONAL TREES FOR ANY |
| | PORTION OF THE REQUIRED MEASUREMENT. |
| | |
| | 5. CONDITIONALLY SATISFIED. PLEASE SHOW LOCATIONS OF |
| | ROOT BARRIERS TO PROTECT INFRASTRUCTURE AND TREES FROM |
| | CONFLICTS. THIS INCLUDES WATER, SEWER, DRAINAGE, |
| | SIDEWALKS AND CURBS, AND ANY FIELD STRUCTURES THAT |
| | COULD BE IMPACTED BY TREE ROOTS. |
| | |
| | 6. CONDITIONALLY SATISFIED. PLEASE PROVIDE SCREENING |
| | FOR ALL GROUND MOUNTED EQUIPMENT AND UTILITIES. |
| | CONDITIONS OF APPROVAL |
| | 1. PRIOR TO THE REMOVAL OR RELOCATION OF ANY TREES ON |
| | THE PROPERTY, A TREE ALTERATION PERMIT SHALL BE |
| | SUBMITTED, REVIEWED AND APPROVED BY THE DEVELOPMENT |
| | SERVICES DEPARTMENT, PLANNING DIVISION. |
| | |
| | 2. PRIOR TO THE ISSUANCE OF THE LANDSCAPE PERMIT, |
| | LOCATIONS OF ROOT BARRIERS TO PROTECT INFRASTRUCTURE |
| | AND TREES FROM CONFLICTS SHALL BE SHOWN ON THE |
| | LANDSCAPE PLAN. THIS INCLUDES WATER, SEWER, DRAINAGE, |
| | SIDEWALKS AND CURBS, AND ANY FIELD STRUCTURES THAT |
| | COULD BE IMPACTED BY TREE ROOTS. |
| | |
| | 3. PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY |
| | FOR THE NEW WAREHOUSE BUILDING, THE APPLICANT SHALL |
| | PROVIDE SCREENING FOR ALL GROUND MOUNTED EQUIPMENT AND |
| | UTILITIES. |
| | |
| | 4. PRIOR TO THE ISSUANCE OF A CERTIFICATE OF OCCUPANCY |
| | FOR THE NEW WAREHOUSE BUILDING, THE APPLICANT SHALL |
| | REMOVE ALL INVASIVE EXOTIC PLANTS FROM THE ENTIRE SITE. |
| | |
| | 5. IF THE LEASED PARKING AREA SHALL CEASE BEING USED BY |
| | THE APPLICANT, THE 5 FOOT LANDSCAPE BUFFER SHALL BE |
| | INSTALLED ON THE PROPERTY ADJACENT TO THE PARKING AREA |
| | WITHIN 6 MONTHS. |
| | |
| |