| 2015-11-24 16:58:42 | AFTER A REVIEW OF THE PPRC RESPONSE LETTER DATED | | | NOVEMBER 16, 2015, FROM THOMAS ENGINEERING GROUP, TO | | | ANA MARIA APONTE, CITY URBAN DESIGNER, THE PREVIOUSLY | | | SUBMITTED FIRE PREVENTION BUREAU COMMENTS WERE NOT | | | NOTED. | | | | | | HOWEVER, THE PREVIOUS COMMENTS BY THE FIRE PREVENTION | | | BUREAU WERE RELATED TO BUILDING CONSTRUCTION PLAN | | | REVIEW. | | | | | | THE PROJECT IS SUPPORTED AND APPROVED BY THE BUREAU. | | | | | | THE BUREAU'S APPROVAL OF THIS SUBMITTED PROJECT DOES | | | NOT CONSTITUTE IT'S FINAL REVIEW OR APPROVAL. | | | | | | THE BUREAU SHALL REVIEW ALL SUBMITTED BUILDING PLANS AT | | | THE APPROPRIATE TIME AND IN ACCORDANCE WITH THE | | | REQUIREMENTS OF ALL APPLICABLE CODES AND STANDARDS. | | | |
| |