| Date |
Text |
| 2016-06-02 12:59:30 | THE FOLLOWING COMMENTS WERE GENERATED AFTER THE REVIEW |
| | OF THE ARCHITECTURAL AND LANDSCAPE PLANS RECEIVED MAY |
| | 3, 2016 BY THE CITY: |
| | |
| | 1. NO ENGINEERING PLANS OTHER THAN A CONCEPTUAL |
| | DRAINAGE PLAN WERE SUBMITTED. |
| | |
| | 2. PROVIDE A SCALE BAR ON THE SURVEY. BASED ON THE |
| | DIMENSIONS LISTED ON THE DRAWING, IT APPEARS THE |
| | GRAPHIC WAS REDUCED AND THE LISTED 1" = 20' SCALE IS |
| | NOT CORRECT. |
| | |
| | 3. THE SITE IS BEING TOTALLY REDEVELOPED. STORMWATER |
| | TREATMENT WILL NEED TO BE PROVIDED IN ACCORDANCE WITH |
| | SFWMD CRITERIA. |
| | |
| | 4. THE STORM PIPE CONNECTION TO THE EXISTING INLET ON |
| | DIXIE HIGHWAY WILL REQUIRE FDOT APPROVAL. DIXIE HIGHWAY |
| | IS A FDOT ROADWAY IN THIS AREA. |
| | |
| | 5. PLEASE PROVIDE SEPARATE DRAWING SHOWING AUTOTURN |
| | ANALYSIS DEMONSTRATING THE SOLID WASTE COLLECTION |
| | VEHICLE CAN ACCESS THE PROPOSED DUMPSTER LOCATION. |
| | |
| | 6. SHOW LIGHT POLES, PROPOSED UTILITIES AND EXISTING |
| | UTILITIES THAT WILL REMAIN ON THE LANDSCAPE PLAN. IT |
| | APPEARS SOME OAKS, CRAPE MIRTLES AND SILVER BUTTONWOOD |
| | TREES ARE PROPOSED NEAR OR OVER SOME OF THE STORM |
| | PIPES. |
| | |
| | 7. EXISTING DRIVEWAY OPENING ON DIXIE HIGHWAY THAT WILL |
| | NO LONGER BE USED WILL NEED TO BE REPLACED WITH |
| | SIDEWALK, CURB AND GUTTER TO MATCH ADJACENT |
| | RIGHT-OF-WAY ITEMS. |
| | |
| | 8. IT APPEARS THE DRIVEWAY ACCESS ON PALM BEACH LAKES |
| | BLVD IS BEING SHIFTED TO THE EAST. THE PORTION OF THE |
| | EXISTING DRIVEWAY THAT WILL NOT BE NEEDED FOR THE |
| | PROPOSED DRIVEWAY WILL NEED TO BE REMOVED AND REPLACED |
| | WITH STANDARD SIDEWALK, CURB AND GUTTER. |
| | |
| | 9. STOP SIGNS WILL BE NEEDED AT ALL DRIVEWAYS TO PUBLIC |
| | RIGHTS OF WAY. |
| | |
| | TRACY L. WARD, P.E. |
| | SENIOR STORMWATER ENGINEER |
| | ENGINEERING SERVICES DEPARTMENT |
| | 561-494-1120 |
| |
Print |